QUESTIONS & SOLUTIONS!
If the operator is setting up the crane alone, which of the following is required?
A. Overhead power lines must be at least 10ft over the boom
B. Wind speed cannot exceed on the Beaufort
C. The red cones designating the work zone must be set up
D. Stabilizers shall be visible to the operator when extending and setting -
ANSWER D. Stabilizers shall be visible to the operator when extending and setting
Before the boom is un-stowed from the transport position which of the following
is most important
A. Wheel chock are set
B. Barricade tape is installed around the work zone
C. Stabilizers are properly extended and set
D. Engine oil level has been checked - ANSWER C
Prior to setting up the crane for a lift, what is one thing the operator should do?
A. Fill out the truck log
B. Perform a function of all the boom controls
C. Extend stabilizer on the lifting side of the Crane
D. Make sure the ground will support the weight of the crane and load - ANSWER
D
, What is the minimum clearance from energized power lines when traveling?
A. 1ft
B. 4ft
C. 6ft
D. 10ft - ANSWER B
Which of the following standards pertain to articulating boom cranes?
A. ASME B-30.5
B ASME B30.9
C ASME B30.22
D. ASME B30.23 - ANSWER C
Material that is slip resistant must be provided for
A. All operation and service locations
B. At each stand up platform control station
C. On the deck of the vehicle
D. Anti slip material is not required anywhere - ANSWER B
When operating the crane using remote control, you should never
A. Walk around the load
B. Follow hand signals from a designated signal person