CCIL EXAM Graded A+ with Questions
Solved 100% Correct
When concrete contains aggregate larger than permitted size, what should you
do before - Answer Wet sieve
Temperature must be obtained how many minutes after sampling - Answer 5 minutes
Air content and slump tests must be completed within —— minutes after remixing -
Answer 10
Volumetric air content method must be started within _______ minutes after
transported and remixed - Answer 5 minutes
CSA 3C gives procedures for __ and __ of test cylinders - Answer Making and curing
Tamping rod must be round straight steel rod with diameter _____ for 100 mm
diameter - Answer 10
Sample used must be in accordance with what procedure - Answer 1C
Cylinder mould 100 mm diameter can be used for particles up to what size - Answer 28
For concrete with slump 100 mm, what consolidation method should be used? - Answer
Rodding
Solved 100% Correct
When concrete contains aggregate larger than permitted size, what should you
do before - Answer Wet sieve
Temperature must be obtained how many minutes after sampling - Answer 5 minutes
Air content and slump tests must be completed within —— minutes after remixing -
Answer 10
Volumetric air content method must be started within _______ minutes after
transported and remixed - Answer 5 minutes
CSA 3C gives procedures for __ and __ of test cylinders - Answer Making and curing
Tamping rod must be round straight steel rod with diameter _____ for 100 mm
diameter - Answer 10
Sample used must be in accordance with what procedure - Answer 1C
Cylinder mould 100 mm diameter can be used for particles up to what size - Answer 28
For concrete with slump 100 mm, what consolidation method should be used? - Answer
Rodding