DRII CBCP EXAM 2024/2025 WITH 100%
ACCURATE SOLUTIONS
1. Being able to answer the question, "What is important to your
business?" is part of what process?
A. Gaining senior management support
B. Getting an executive sponsor
C. Developing a budget
D. Defining a business continuity problem statement - Precise Answer
✔✔D.
Defining a business continuity problem statement
2. What is the value of a BCM policy statement?
A. It forces middle management to comply with senior directives
B. It shows employees how to do their part in the planning process
C. It shows management's commitment to BC planning process
D. It provides senior management a direction in which to make future
decisions - Precise Answer ✔✔C.
It shows management's commitment to BC planning process
,3. What would be evidence of management support for BCM?
A. A steering committee that reports to the emergency response team
B. An executive sponsor who reports to the damage assessment
committee
C. A project plan developed solely by the business continuity planner
D. A BCM staff with a budget - Precise Answer ✔✔D.
A BCM staff with a budget
4. What is a benefit to the organization of having an effective business
continuity program?
A. Internal disasters will not go unreported
B. The business continuity program will relate to organizational mission,
objectives, and operations
C. Employees will be amazed at the organization's multi-faceted
response to a disaster
D. The survivability of the organization when faced with a disaster -
Precise Answer ✔✔D.
The survivability of the organization when faced with a disaster
, 5. What must the planner avoid when developing a business continuity
program?
A. Obtaining management support
B. Personally determining what is critical to the organization
C. Organizing and managing the project
D. Completing the project within agreed upon time and budget limits -
Precise Answer ✔✔B.
Personally determining what is critical to the organization
6. Why is it important to track and report project progress?
A. To communicate up to management, laterally to other programs, and
down to project members
B. To conduct meetings to ensure that all members of the organization
share responsibility in the project plan
C. To involve all organizational personnel in developing and adjusting
scope
D. To validate that the planning team is sticking to the project plan -
Precise Answer ✔✔A.
To communicate up to management, laterally to other programs, and
down to project members
ACCURATE SOLUTIONS
1. Being able to answer the question, "What is important to your
business?" is part of what process?
A. Gaining senior management support
B. Getting an executive sponsor
C. Developing a budget
D. Defining a business continuity problem statement - Precise Answer
✔✔D.
Defining a business continuity problem statement
2. What is the value of a BCM policy statement?
A. It forces middle management to comply with senior directives
B. It shows employees how to do their part in the planning process
C. It shows management's commitment to BC planning process
D. It provides senior management a direction in which to make future
decisions - Precise Answer ✔✔C.
It shows management's commitment to BC planning process
,3. What would be evidence of management support for BCM?
A. A steering committee that reports to the emergency response team
B. An executive sponsor who reports to the damage assessment
committee
C. A project plan developed solely by the business continuity planner
D. A BCM staff with a budget - Precise Answer ✔✔D.
A BCM staff with a budget
4. What is a benefit to the organization of having an effective business
continuity program?
A. Internal disasters will not go unreported
B. The business continuity program will relate to organizational mission,
objectives, and operations
C. Employees will be amazed at the organization's multi-faceted
response to a disaster
D. The survivability of the organization when faced with a disaster -
Precise Answer ✔✔D.
The survivability of the organization when faced with a disaster
, 5. What must the planner avoid when developing a business continuity
program?
A. Obtaining management support
B. Personally determining what is critical to the organization
C. Organizing and managing the project
D. Completing the project within agreed upon time and budget limits -
Precise Answer ✔✔B.
Personally determining what is critical to the organization
6. Why is it important to track and report project progress?
A. To communicate up to management, laterally to other programs, and
down to project members
B. To conduct meetings to ensure that all members of the organization
share responsibility in the project plan
C. To involve all organizational personnel in developing and adjusting
scope
D. To validate that the planning team is sticking to the project plan -
Precise Answer ✔✔A.
To communicate up to management, laterally to other programs, and
down to project members