Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Exam (elaborations)

Applied Statistics in Business and Economics Final Exam (Chapters 6&7) 7th Edition by David Doane & Lori Sewar

Rating
-
Sold
-
Pages
6
Grade
A+
Uploaded on
16-09-2024
Written in
2024/2025

Applied Statistics in Business and Economics Final Exam (Chapters 6&7) 7th Edition by David Doane & Lori Sewar To save time, you use information from a similar project to help you estimate your activity durations. This is an example of which tool or technique? A. Bottom-up estimating B. Analogous estimating C. Parametric estimating D. Three-point estimating - CORRECT ANSWER-B is correct. Analogous estimating involves using information from similar projects (i.e., an analogy) to estimate elements of your project. This is generally less costly and time consuming than other techniques. What is the authorized time-phased budget at completion used to measure, monitor, and control overall cost performance on the project more commonly known as? A. Approved project budget B. Cost baseline C. Activity cost estimates D. Total funding requirements - CORRECT ANSWER-B is correct. The cost baseline is the aggregation of the Estimate Cost and Determine Budget processes. You assign one of your junior staff to track the actual start and finish of activities and milestones to ensure they are being performed against the planned timeline. Which of the following processes is most consistent with these activities? A. Control Scope B. Control Schedule C. Monitor Communications D. Monitor Risks - CORRECT ANSWER-B is correct. Control Schedule is the process of ensuring that the project will produce its required deliverables and solutions on time. The activities in this process include tracking the actual start and finish of activities and milestones against the planned timeline and updating the plan so that the comparison to the plan is always current. If there is a delay in your project schedule, you could:

Show more Read less
Institution
Applied Statistics
Module
Applied Statistics

Content preview

Applied Statistics in Business and Economics Final Exam
(Chapters 6&7) 7th Edition by David Doane & Lori Sewar
To save time, you use information from a similar project to help you estimate your activity durations. This
is an example of which tool or technique?

A. Bottom-up estimating

B. Analogous estimating

C. Parametric estimating

D. Three-point estimating - CORRECT ANSWER-B is correct. Analogous estimating involves using
information from similar projects (i.e., an analogy) to estimate elements of your project. This is generally
less costly and time consuming than other techniques.



What is the authorized time-phased budget at completion used to measure, monitor, and control overall
cost performance on the project more commonly known as?

A. Approved project budget

B. Cost baseline

C. Activity cost estimates

D. Total funding requirements - CORRECT ANSWER-B is correct. The cost baseline is the aggregation of
the Estimate Cost and Determine Budget processes.



You assign one of your junior staff to track the actual start and finish of activities and milestones to
ensure they are being performed against the planned timeline. Which of the following processes is most
consistent with these activities?

A. Control Scope

B. Control Schedule

C. Monitor Communications

D. Monitor Risks - CORRECT ANSWER-B is correct. Control Schedule is the process of ensuring that the
project will produce its required deliverables and solutions on time. The activities in this process include
tracking the actual start and finish of activities and milestones against the planned timeline and updating
the plan so that the comparison to the plan is always current.



If there is a delay in your project schedule, you could:

, A. Change the due date of the project

B. Fast track or crash the project and let the steering committee know the impact of your action

C. Ask the project staff to work overtime until the project deadlines are met

D. Reduce the project scope - CORRECT ANSWER-B is correct. Crashing a project schedule involves
bringing in more resource to do the work. Extra resources usually cost more money. Fast tracking on the
other hand involves completing activities in parallel that might normally be done in sequence. This does
not always cost more money.



You are working on a large project and have determined that your cost variance (CV) is $50,000 and that
your earned value (EV) is $125,000. What is your actual cost (AC)?

A. $75,000

B. $50,000

C. $175,000

D. $125,000 - CORRECT ANSWER-A is correct. The formula for Cost Variance is CV = EV − AC. Therefore, if
CV = $50,000 and EV = $125,000, then AC must equal $75,000.



You are calculating the amount of float on various paths in the network diagram to determine the
minimum project duration. What tool or technique are you using?

A. Critical path method

B. Critical chain method

C. Parametric estimating

D. Three-point estimating - CORRECT ANSWER-A is correct. Critical path methodology focuses on the
amount of float in network paths to determine the critical path through a project. The critical path has
no float associated with it and as such represents the greatest risk to the project duration.



Your project has a CPI of 1.1 and an SPI of 0.9. What does this mean?

A. You are experiencing a cost underrun and are ahead of schedule

B. You are experiencing a cost overrun and are behind schedule

C. You are experiencing a cost underrun and are behind schedule

D. You are experiencing a cost overrun and are ahead of schedule - CORRECT ANSWER-C is correct. A CPI
above 1 means a cost underrun, whereas an SPI below 1 means you are not achieving all the work you
had planned within the time frame you are measuring.

Written for

Institution
Applied Statistics
Module
Applied Statistics

Document information

Uploaded on
September 16, 2024
Number of pages
6
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

  • monitor risks
  • expert judgment
$3.49
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
LmstopAchiever Northwestern Oklahoma State University
View profile
Follow You need to be logged in order to follow users or courses
Sold
25
Member since
4 year
Number of followers
8
Documents
278
Last sold
2 months ago

3.5

4 reviews

5
2
4
0
3
1
2
0
1
1

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions