Using CPM to evaluate the project represented by the following data, which of
the following tasks are not on the critical path?: A, 5, N/A; B, 8 N/A; C, 6, A,B; D,
7, C; E, 3, D; F, 4, D; G, 9, F; H, 4, E,G; Answer - A
In the PMBOK, the logical groupings of the five project management processes
to achieve specific project objectives are called the: Answer - project
management process groups
Which of the following responses identifies a common type of logical
dependency used to sequence project activities? Answer - Finish-to-start
You are the project manager for a software development project that is using
the SDLC and are about to begin integration testing. With what should you be
primarily concerned? Answer - Verifying the scope
Quality control activities generally include all of the following EXCEPT:
Answer - Management by objectives
Figure 7-3 System Integration Project
Consider the System Integration Project depicted in Figure 7-3. Based on the
information provided, which activities can be delayed one day without
impacting the expected project completion date? Answer - Activity C -
Purchase Software and Activity D - Prepare Test Plan
, Which estimating technique decomposes the work into lower, more detailed
pieces, preferably the lowest level of WBS work elements, for which estimates
are prepared and then aggregates them into a total quantity for the project?
Answer - bottom-up estimating
Adding additional resources to reduce the schedule time a task or activity is
called what? Answer - Crashing
Your project is large, will take 3 years, & will be highly visible to sr. leadership.
Your company does not manage risks well & rarely follows its risk management
policies and procedures. If management wants to see an analysis of the risk
strategies which of the following is least important? Answer - The sponsor
Which of the following charter elements defines the project purpose and
justifies the necessity of the project? Answer - Business case
Which of the following is a reason to authorize a project? Answer - A. A market
demand
b. A regulatory requirement
Correct c. All of the above
d. A specified organizational need
A project receives a major scope change that is the 4th major overhaul of the
project. The PM finds a key deliverable did not meet quality standards as a
resource was moved off the project to work another troubled project. With