iQMS Orientation for BPS Exam Questions & Answers 2024/2025 Which of the following are Process Handbooks in iQMS? -Policies -Procedures -Business process services Process handouts -Testing Guidelines -Project Procedures Manual - ANSWERSBusiness process services Process handouts During which stage of the project lifestyle, is Customer Satisfaction Survey... -At the end of the project -At the end of six months -At the end of four months -At the end of the project or at the end of six months, which... -At the end of the project or at the end of four months, which... - ANSWERSAt the end of the project or at the end of six months, which... What does the Loyalty parameter in the Customer Satisfaction... -Loyalty of Customer among other customers -Customer would recommend TCS within and outside... -Customer would recommend project lead within and... -All of the above -None of the above - ANSWERSCustomer would recommend TCS within and outside... While developing the initial plan for your project, the team has made 15..... -Assumptions are definitely an input to risk identification -Assumptions can be changed, so it does not matter

Content preview

iQMS Orientation for BPS Exam
Questions & Answers 2024/2025

Which of the following are Process Handbooks in iQMS?

-Policies

-Procedures

-Business process services Process handouts

-Testing Guidelines

-Project Procedures Manual - ANSWERSBusiness process services Process handouts



During which stage of the project lifestyle, is Customer Satisfaction Survey...

-At the end of the project

-At the end of six months

-At the end of four months

-At the end of the project or at the end of six months, which...

-At the end of the project or at the end of four months, which... - ANSWERSAt the end of the project or
at the end of six months, which...



What does the Loyalty parameter in the Customer Satisfaction...

-Loyalty of Customer among other customers

-Customer would recommend TCS within and outside...

-Customer would recommend project lead within and...

-All of the above

-None of the above - ANSWERSCustomer would recommend TCS within and outside...



While developing the initial plan for your project, the team has made 15.....

-Assumptions are definitely an input to risk identification

-Assumptions can be changed, so it does not matter

,-There is no time to relook at the Assumptions. The team should..

-The team is equipped to handle all scenarios - ANSWERSAssumptions are definitely an input to risk
identification



Which among the following is the TCS Quality Policy?

-To achieve customer and other stakeholders satisfaction by delivering solutions which meet their need...

-To become the top most IT services Organization across the globe

-To ensure "Experience Certainty"

-None of the above - ANSWERSTo achieve customer and other stakeholders satisfaction by delivering
solutions which meet their need...



Which of the following defines the manual for 5D life cycle phases for Business services and deliverable...

-Guidelines and Standards

-Business Processes Services Process Handbook

-Project Procedures Manual for Business Process Services

-Estimation guidelines - ANSWERSBusiness Processes Services Process Handbook



In which of the following conditions is the overall cause mandated for a Customer Satisfaction...

A) CSI is below 85%

B) Recommendation rating is 'Probably Not' or 'Definitely Not'

C) TCS rank is 'Third' or 'Not in Top Three' - ANSWERSA,B and C



Which of the following graphical tools is used to monitor process variable over time and time and helpful
in identifying trends and cycles?

-Pareto Chart

-Pie Chart

-Run Chart

-Histogram - ANSWERSRun Chart



Which of the following are the components of Cost of Quality (CoQ)?

, -All efforts other than SDLC efforts

-Prevented, Appraisal and Rework

-Cost of finding and removing defects

% effort spent on incorporating CRs - ANSWERSPrevented, Appraisal and Rework



Which of the following Project Management area are covered in a Project Management Review (PMR)

-Customer Relationship Health

-Process Health

-Product Health

-Financial Health

-All of these - ANSWERSAll of these



During Change Management, in what sequence are the following activities carried out?

A. Accept and authorize the Change

B. Review the Change implemented and sign off

C. Review and recommend processing of the Change request

D. Raise a Change Request

E. Evaluate, Prioritize and Conduct impact Analysis

F. Implement/ Monitor the Change - ANSWERSD,E,C,A,F,B



There are several steps in Risk management and one of them is Risk Response Planning for the threats or
risks that could negatively impact your project. Which of the following activates are part of Risk response
Planning?

-Reducing project threats

-Identifying risks

-Risk owner deciding the appropriate risk response (Reduce, Accept, Avoid, Transfer)based on the risk
exposure

-Determining whether the risk has occurred - ANSWERSRisk owner deciding the appropriate risk
response (Reduce, Accept, Avoid, Transfer)base on the risk exposure

Document information

Uploaded on
September 11, 2024
Number of pages
17
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$9.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Bensuda
3.7
(164)
Sold
902
Followers
445
Items
23098
Last sold
3 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions