NC Water & Sewer -
Erosion and
Sedimentation Control
with 100% correct
answers
1 - Which of the below would require an approved
erosion and sedimentation control plan before any
clearing or grading may occur?
1 - Less than ½ acre
2 - Over ½ acre
3 - 1 acre
4 - Over 1 acre - answer Over 1 acre
2 - Erosion and sedimentation control plans must
be submitted how many days in advance of the
start of clearing or grading?
1 - 7 days
2 - 14 days
, 3 - 30 days
4 - 90 days - answer 30 days
3 - Which of the below are true about erosion and
sedimentation control?
1 - Surfaces must be stabilized
2 - Sediment must be retained on site
3 - Don't start work before plan approval
4 - All of these - answer All of these
4 - Who is responsible for erosion control?
1 - EPA
2 - NC Erosion Control Agency
3 - Local Government
4 - Person financially responsible for land
disturbing activity - answer Person financially
responsible for land disturbing activity
5 - In addition to the person financially responsible
for the land disturbing activity who else may be
held responsible for erosion control?
Erosion and
Sedimentation Control
with 100% correct
answers
1 - Which of the below would require an approved
erosion and sedimentation control plan before any
clearing or grading may occur?
1 - Less than ½ acre
2 - Over ½ acre
3 - 1 acre
4 - Over 1 acre - answer Over 1 acre
2 - Erosion and sedimentation control plans must
be submitted how many days in advance of the
start of clearing or grading?
1 - 7 days
2 - 14 days
, 3 - 30 days
4 - 90 days - answer 30 days
3 - Which of the below are true about erosion and
sedimentation control?
1 - Surfaces must be stabilized
2 - Sediment must be retained on site
3 - Don't start work before plan approval
4 - All of these - answer All of these
4 - Who is responsible for erosion control?
1 - EPA
2 - NC Erosion Control Agency
3 - Local Government
4 - Person financially responsible for land
disturbing activity - answer Person financially
responsible for land disturbing activity
5 - In addition to the person financially responsible
for the land disturbing activity who else may be
held responsible for erosion control?