CAPM Exam Prep - Planning Process
1. As a project manager you'll need to gather the stakeholder requirements your
project is required to satisfy to consider the project complete: -
Answer✔️ ✔C ️ ollect Requirements
2. Once you've created the project scope and the WBS, the project manager and
project team will define the exact activities that need to complete in order to
create the elements of the WBS and scope - Answer✔️ ✔️ Define Activities
3. Based on the needs of the project, the organizational procedures, and the
project budget, the procurements for the project are identified and planned
for - Answer✔️ ✔P ️ lan Procurements
4. Once you've created the Project Scope Statement, you'll decompose the
project scope into this document - Answer✔️ ✔️Work Breakdown Structure
5. Once you've created the WBS, you can examine the aggregate costs of the
individual elements to create a budget and a cost baseline -
Answer✔️ ✔D ️etermine Budget
6. Based on the stakeholder requirements the project scope statement defines
what is and is not included in the project - Answer✔️✔D️ efine Scope
, 7. Stakeholders will need you and the project team to create time estimates for
the duration of the project work and the duration of the project -
Answer✔️ ✔E ️ stimate Activity Durations
8. The organizational rules and structure may restrict the extent of this process,
which establishes the ground rules, management, discipline, rewards and
recognition system, and other facets of human resource management for the
project - Answer✔️ ✔️ Develop Resource Management Plan
9. There are seven of these that can be used within this risk management
processes - Answer✔️ ✔️ Plan Risk Responses
10.This is an iterative project management process that examines the project for
risks that may threaten any of the project objectives - Answer✔️✔️ Identify
Risks
11.This process determines the people, materials, equipment, and other
necessities to complete the project work - Answer✔️ ✔️ Estimate Activity
Resources
12.This project management process defines the risk management approach to
be used within the project - Answer✔️
✔️ Plan Risk Management
13.This process is based on the outputs of the Qualitative Risk Analysis. It is an
in-depth review of the identified risks - Answer✔️ ✔P ️erform Quantitative
Risk Analysis
14.This project management planning process defines who will get what
information and when - Answer✔️ ✔P ️ lan Communications Management
1. As a project manager you'll need to gather the stakeholder requirements your
project is required to satisfy to consider the project complete: -
Answer✔️ ✔C ️ ollect Requirements
2. Once you've created the project scope and the WBS, the project manager and
project team will define the exact activities that need to complete in order to
create the elements of the WBS and scope - Answer✔️ ✔️ Define Activities
3. Based on the needs of the project, the organizational procedures, and the
project budget, the procurements for the project are identified and planned
for - Answer✔️ ✔P ️ lan Procurements
4. Once you've created the Project Scope Statement, you'll decompose the
project scope into this document - Answer✔️ ✔️Work Breakdown Structure
5. Once you've created the WBS, you can examine the aggregate costs of the
individual elements to create a budget and a cost baseline -
Answer✔️ ✔D ️etermine Budget
6. Based on the stakeholder requirements the project scope statement defines
what is and is not included in the project - Answer✔️✔D️ efine Scope
, 7. Stakeholders will need you and the project team to create time estimates for
the duration of the project work and the duration of the project -
Answer✔️ ✔E ️ stimate Activity Durations
8. The organizational rules and structure may restrict the extent of this process,
which establishes the ground rules, management, discipline, rewards and
recognition system, and other facets of human resource management for the
project - Answer✔️ ✔️ Develop Resource Management Plan
9. There are seven of these that can be used within this risk management
processes - Answer✔️ ✔️ Plan Risk Responses
10.This is an iterative project management process that examines the project for
risks that may threaten any of the project objectives - Answer✔️✔️ Identify
Risks
11.This process determines the people, materials, equipment, and other
necessities to complete the project work - Answer✔️ ✔️ Estimate Activity
Resources
12.This project management process defines the risk management approach to
be used within the project - Answer✔️
✔️ Plan Risk Management
13.This process is based on the outputs of the Qualitative Risk Analysis. It is an
in-depth review of the identified risks - Answer✔️ ✔P ️erform Quantitative
Risk Analysis
14.This project management planning process defines who will get what
information and when - Answer✔️ ✔P ️ lan Communications Management