APM PFQ Definition define the term 'project' - correct answer A unique, transient endeavour undertaken to bring about change and to achieve planned objectives define the term 'project management' - correct answer The application of processes, methods, skills, knowledge, and experience to achieve specific project objectives for change according to the project acceptance criteria within agreed parameters. state the key purpose of project management - correct answer To effect beneficial change define the terms 'programme management' - correct answer The coordinated management of projects and business-as-usual (steady- state) activities to achieve beneficial change Define 'portfolio management' - correct answer The selection, prioritisation and control of an organisation's projects and programmes in line with its strategic objectives and capacity to deliver. (Portfolios balance the implantation of change initiative and maintain BAU, while optimising on investment. Portfolios can be managed at an organisational or functional level to optimise strategic benefits or operational efficiency, respectively) Define Programmes - correct answer unique, transient, strategic endeavours undertaken to achieve beneficial change and they incorporate a group of related projects and BAU activities. What are programmes measure of success? - correct answer Programmes measure of success Is the actual realisation of the expected benefits Define PESTLE - correct answer Political - current and potential influences from political pressures Economic - local, national and world economic impact Sociological - the effect of changes in the needs of society

Content preview

APM PFQ Definition


define the term 'project' - correct answer ✔✔A unique, transient endeavour undertaken to bring about
change and to achieve planned objectives



define the term 'project management' - correct answer ✔✔The application of processes, methods,
skills, knowledge, and experience to achieve specific project objectives for change according to the
project acceptance criteria within agreed parameters.



state the key purpose of project management - correct answer ✔✔To effect beneficial change



define the terms 'programme management' - correct answer ✔✔The coordinated management of
projects and business-as-usual (steady- state) activities to achieve beneficial change



Define 'portfolio management' - correct answer ✔✔The selection, prioritisation and control of an
organisation's projects and programmes in line with its strategic objectives and capacity to deliver.

(Portfolios balance the implantation of change initiative and maintain BAU, while optimising on
investment.

Portfolios can be managed at an organisational or functional level to optimise strategic benefits or
operational efficiency, respectively)



Define Programmes - correct answer ✔✔unique, transient, strategic endeavours undertaken to achieve
beneficial change and they incorporate a group of related projects and BAU activities.



What are programmes measure of success? - correct answer ✔✔Programmes measure of success Is the
actual realisation of the expected benefits



Define PESTLE - correct answer ✔✔Political - current and potential influences from political pressures

Economic - local, national and world economic impact

Sociological - the effect of changes in the needs of society

,Technological - new and emerging technology

Legal - local, national and world legalisation

Environmental - local, national and world environmental issues



describe why PESTLE analysis might be used by a project manager - correct answer ✔✔PESTLE is a
management technique to help the project management understand the environment in which the
project operates. These show the external or internal influences of success or failure.

One strength of a business case is to show that the organisation has not become over reliant on a single
idea



state the phases of a typical linear project life cycle - correct answer ✔✔Concept - development of an
initial idea through initial studies and high-level requirement management and assessment of viability,
including an outline business case

Definition - development of a detailed definition, plan and statement of requirements that include a full
justification for the work. PMP is formed in this stage

Deployment - implantation of plans, verification of performance through testing and assurance to realise
intended outputs, outcomes, and benefits.

Transition - handover, commissioning, and acceptance of outputs to the sponsor and wider users,
culminating in formal closure.



What is the "Predictive approach" to creating a life cycle - correct answer ✔✔rely on knowledge
identified at the start, allowing work to proceed in a sequential manner



What is the "Adaptive approach" to creating a life cycle - correct answer ✔✔implies new knowledge is
created as the work progresses, which is then used to inform and guide the remaining effort



state the phases of a typical iterative project life cycle - correct answer ✔✔Pre-Project - developing a
high-level vision

Feasibility and Foundations - finer details are uncovered during cycles of iteration

Evolutionary development - specification and design to run in parallel

Deployment - bring the evolving solution into operational use either fully or using an incremental
solution that delivers partial requirements, using user experience to form the next solution increments.

,Postproject - identifies whether the solution has delivered the benefits to the degree required to
achieve the business case



define the term 'hybrid life cycle' - correct answer ✔✔A pragmatic approach to achieving beneficial
change that combines a linear life cycle for some phases or activities with an iterative life cycle for
others.



What are the benefits for a hybrid life cycle? - correct answer ✔✔Adding iterative elements to
"predictive" projects can enhance deployment stages, support the generation of insights, underpin the
realisation of an early benefit, and validate some of the ideas much earlier in the cycle.

Building agile into a project/programme can offer increased efficiency and flexibility, however it requires
great skill and clarity when using multiple different systems of working



define the term 'extended project life cycle' - correct answer ✔✔A life cycle approach that adds an
adoption phase to a linear or iterative life cycle with the purpose of ensuring the accountability and
governance of the investment stays with the change teams until change is fully embedded. It provides
the missing connection to benefit realisation in a linear life cycle and facilitates cooperation and
knowledge sharing between change and business-as-usual teams.



When does the extended life cycle happen? - correct answer ✔✔After the transition phase



What are the two phases that are part of the extended life cycle? - correct answer ✔✔Adoption -
operations and sustainment required to utilise the new project and enable the acceptance and use of
the benefits



Benefits realisation - realisation of the required business benefits



Outline project management roles and responsibilities: Project Sponsor - correct answer ✔✔project
sponsor:

- Primary risk taker and has ultimate accountability and overall responsibility for the project.

- Most likely to have managed the project through the initial phase

- Responsible for ensuring the projects benefits are realised when the project is handed back to
operations.

- A member of the and has delegated authority of the steering group, as a chairperson

, - Assists in business management and project management issues that arise outside the formal issues of
the steering group

- Lends support by advocacy at the senior level

- Ensures necessary recourse are available for the project

- Responsibilities include:

o Arbiter for user and stakeholder requirements

o Determining the relative priority of time, cost, and quality

o Initiating the project and ensuring PM appointed

o Monitoring high level progress and making control decisions when necessary

o Monitoring business environment and reviewing the business case at gate reviews

o Keeping senior management involved of project progress

o Terminating the project if necessary, after gate review

o Developing and maintaining ownership of the business case



Outline project management roles and responsibilities: Project Manager - correct answer ✔✔Project
manager

- To plan, organise, staff, motivate, evaluate, direct, control and lead the project from start to finish to
deliver the project objectives.

- Responsibilities include:

o Delivering on time, cost, quality/performance priorities

o Making timely decisions

o Communicating with the sponsor, forming them of progress and seeking direction when necessary

o Managing sponsor and user expectations

o Defining and planning the project through creation of PMP

o Monitoring and controlling project progress

o Building, leading, and motivating the project team

o Ensuring work packages are allocated and responsibilities identified

o Initiating reviews and assisting the sponsor in making the decision to terminate (if justified)

o Communicating as prime point of contact with team members, other organisations, contractors,
suppliers, and operations representatives.

Document information

Uploaded on
August 16, 2024
Number of pages
35
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$8.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Studyclass
3.4
(11)
Sold
28
Followers
12
Items
4570
Last sold
7 months ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions