Choose the proper sequence of the Defense Acquisition Process phases. -
ANSWER>>Materiel Solution Analysis (MSA), Technology Maturation and Risk
Reduction (TMRR), Engineering and Manufacturing Development (EMD), Production and
Deployment (P&D), Operations and Support (O&S)
Systems Engineering: (Select all that apply.) - ANSWER>>
Product Support Execution includes: (Select all that apply.) -
ANSWER>>Implementation of all the support functions, processes and activities
required to maintain a system at its intended level of operation in the field
The definition of product support development includes: - ANSWER>>Technical and
management activities, supportability implications during the acquisition process,
minimization of support costs, and providing the user with resources for sustainment.
Life cycle logisticians participate in Integrated Product Teams that deal with: -
ANSWER>>Logistics, systems engineering, cost performance, and test and evaluation
Integrated Product and Process Development: - ANSWER>>All of the choices are
correct
The LCL must ensure that the acquisition strategy includes appropriate ___________
metrics for building __________ into the system design and developing life cycle product
support strategies designed to deliver the product support package. -
ANSWER>>Performance, supportability
The Joint Capabilities Integration and Development Systems is part of the acquisition
process with the decision support systems of: (Select all that apply.) - ANSWER>>-
Defense Acquisition System
- Planning, Programming, Budgeting and Execution
, Stakeholder Requirements - ANSWER>>Takes all inputs from users and stakeholders,
clarifies them as necessary and translates these inputs into Technical Requirements
Architecture Design - ANSWER>>Translates the outputs of Requirements Definition
and Analysis processes into alternate design solutions and ultimately a final design
solution
Integration - ANSWER>>Incorporation of lower-level system elements into higher-
level subsystems and systems
Validation - ANSWER>>Confirmation that a system element meets its Stakeholder
Requirements
The life cycle logistician is responsible for understanding user requirements while
serving on an Integrated Product Team. User requirements include: -
ANSWER>>Customer performance and cost requirements
Product support execution consists of: (Select all that apply.) - ANSWER>>-
Provisioning training
- Provisioning personnel
- Provisioning logistics
What is the role of the life cycle logistician on an Integrated Product Team? (Select all
answers that apply) - ANSWER>>- Integrate logistics products and processes into the
overall system capability
- Respond to and account for changes from other functional areas that impact product
support planning
- Influence the system design for supportability