CCCA Exam Questions & Answers 2024/2025 Preliminary Project Description PPD - ANSWERSdescribes the scope and relationships of major elements organized in terms of building systems and components - CSI recommends UniFormat for PPDS - describes as a system of components Outline specifications - ANSWERSan abbreviated set of specification requirements normally included with schematic design or design development documents. Bassi for revising estimates of cost/schedule value - Record decisions shop drawing - ANSWERSnot a contract document - repared by contractor / sub/equipment supplier and show how an aspect of the work is to be fabricated and installed methods of specifying - ANSWERSDescriptive, performance, reference standards, proprietary Descriptive Specification - ANSWERSdetailed description of required properties of product. A/E responsible for determination of desired performance criteria Performance Specifications - ANSWERSrequired result with criteria for verifying compliance Proprietary specifications - ANSWERSidentify the desired manufacture or unique characteristic closed vs open proprietary specification - ANSWERS Two types of bonds - ANSWERSperformance bond and payment bond When are bonds expected to be delievered? - ANSWERSTo the owner when the contractor delivers the executed owner-contractor agreements

Content preview

CCCA Exam Questions & Answers
2024/2025

Preliminary Project Description PPD - ANSWERSdescribes the scope and relationships of major elements
organized in terms of building systems and components - CSI recommends UniFormat for PPDS -
describes as a system of components



Outline specifications - ANSWERSan abbreviated set of specification requirements normally included
with schematic design or design development documents. Bassi for revising estimates of cost/schedule
value - Record decisions



shop drawing - ANSWERSnot a contract document - repared by contractor / sub/equipment supplier and
show how an aspect of the work is to be fabricated and installed



methods of specifying - ANSWERSDescriptive, performance, reference standards, proprietary



Descriptive Specification - ANSWERSdetailed description of required properties of product. A/E
responsible for determination of desired performance criteria



Performance Specifications - ANSWERSrequired result with criteria for verifying compliance



Proprietary specifications - ANSWERSidentify the desired manufacture or unique characteristic



closed vs open proprietary specification - ANSWERS



Two types of bonds - ANSWERSperformance bond and payment bond



When are bonds expected to be delievered? - ANSWERSTo the owner when the contractor delivers the
executed owner-contractor agreements

,What are bonds - ANSWERSThey are not insurance



What protects the owner against mechanics liens? - ANSWERSPayment bond



What protects suppliers and subs against nonpayment? - ANSWERSPayment bond



Surety bond - ANSWERSAKA contract bond



Performance Bond - ANSWERSguaranty that if the contractor fails to perform, the surety will either
complete the contract or provide sufficient funds up to the penalty sum for such completion



Other bonds in addition to performance and payment bonds - ANSWERSmaintenance bonds, lien bonds,
retainage bonds (alternative to retainage), license and permit bonds (from AHJs)



Who is responsible for coordinating work to be completed under separate contracts? - ANSWERSOwner



Preliminary schedules must be submitted at least 10 days after the effective date of the contract -
ANSWERSAccording to many general standard conditions - ConsensusDocs doesn't have this
requirement



Two most frequently used schedule formats - ANSWERScritical path method (CPM)

bar chart



Approval for schedule by contractor - ANSWERSA/E reviews for compliance with contracts - Owner
determines if it meets requirements - In some contracts, schedule revisions are allowed only by change
order



Comprehensive schedule AKA project schedule - ANSWERSoften a critical path schedule beginning with
the inception of the project and concludes with final acceptance



schedule of values - ANSWERScomplements the progress schedule

, identifies how all the costs int he project are apportioned



A/E can request supporting documentation from contractor when thee is a disagreement on the
proportionate value of items of work



Change orders are usually added to schedule of values



What records does the A/E maintain? - ANSWERSfield observation reports

documentation of non-confirming work

correspondence

meeting minutes

communication reports

submittals

test reports

payment requests and certifications

schedule

requests for interpretation, clarification or information

proposal requests or change order requests

contract document modifications



Submittal Log - ANSWERSshould be maintained by both the A/E and contractor

should have specification section reference

dates

action taken (approve, approved as noted, revise/resubmit, rejected,resubmit,no action,not requried for
review)



Daily log - ANSWERSwork performed, delivery of products, construction problems/remedies,
documentation of delays, observation of nonconforming work, visitors to the site, inspections
performed, test take, signature and date

Document information

Uploaded on
August 3, 2024
Number of pages
18
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$8.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Bensuda
3.7
(164)
Sold
900
Followers
445
Items
23098
Last sold
3 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions