ACG Guideline with Complete SolutionsACG Guideline with Complete SolutionsACG Guideline with Complete SolutionsACG Guideline with Complete Solutions What are the five phases of commissioning? - ANSWER-1.) Pre-Design 2.) Design 3.) Construction 4.) Acceptance 5.) Post-Acceptance Studies indicate _ to _% savings in building operating costs when comparing a comissioned building to a non-commissioned building. - ANSWER-8 to 20% What is commissioning? - ANSWER-A process of documentation, adjustment, testing, verification, and training performed specifically to ensure that the finished facility operates in accordance with the owner's documented project requirements and the construction documents. Commissioning serves the owner's best interests by delivering a facility with systems that perform as specified, intended, and paid for.