AIC Prep UH A 'place concrete' activity requires the placement of 2080 cubic yards. If the individual production rate is 2 cubic yards per work hour per person, with a 10-person crew and 8 hour workday, how many days are needed to complete this activity? a. 13 b. 26 c. 104 d. 130 - ANSWER-a. 13 A topographical map is a drawing showing? a. Subsurface soil conditions b. A general profile view of the site c. Contour lines and elevations d. Cross sections along the length of the project - ANSWER-c. Contour lines and elevations The owner's rep observed substandard drywall patches on a general contractor's renovation project. Which of the following should be the representative's first course of action? a. Save items for punch list b. Notify drywall finisher of the problem c. Tell painter not to accept patched walls. d. Notify general contractors superintend of problem - ANSWER-d. Notify general contractors superintend of problem Five Contractors are bidding part of a job with storm sewer, sanitary sewer, and water distribution. Their bids are: Contractor 1 will do storm and water for $2000. Contractor 2 will do storm for $1000. Contractor 3 will do sanitary and water for $12,000. Contractor 4 will do sanitary for $7,000 Contractor 5 will do water for $7,000 What is the lowest price for the complete job? a. $7
Document information
- Uploaded on
- March 6, 2024
- Number of pages
- 41
- Written in
- 2023/2024
- Type
- Exam (elaborations)
- Contains
- Questions & answers