Answers
The processes required to define the scope of the project, refine the objectives,
and determine the appropriate course of action to achieve the project objectives.
A. Executing process group
B. Monitoring and controlling process group
C. Scoping process group
D. Planning process group - CORRECT ANSWER Workbook, CAPM Final Practice
Exam, page 210, #1
Answer: D
The processes that track, review, and regulate the performance and progress of
the project.
A. Evaluating process group
B. Executing process group
C. Monitoring and controlling process group
D. Planning process group - CORRECT ANSWER Workbook, CAPM Final Practice
Exam, page 210, #2
Answer: C
The processes that are performed to complete the work of the project as defined
in the project management plan.
A. Conduct process group
,B. Executing process group
C. Planning process group
D. Integration process group - CORRECT ANSWER Workbook, CAPM Final Practice
Exam, page 210, #3
Answer: B
This process group includes processes spanning all ten knowledge areas:
A. Initiating process group
B. Executing process group
C. Planning process group
D. Monitoring and controlling process group - CORRECT ANSWER Workbook,
CAPM Final Practice Exam, page 210, #4
Answer: C
The majority of the project team's time, efforts, and expense are applied during
this process group:
A. Planning process group
B. Executing process group
C. Integration process group
D. Monitoring and controlling process group - CORRECT ANSWER Workbook,
CAPM Final Practice Exam, page 210, #5
Answer: B
,Includes status reports, information notes, electronic dashboards, justifications,
memos, etc.
A. Work performance information
B. Work performance data
C. Work performance reports
D. Work performance outputs - CORRECT ANSWER Workbook, CAPM Final
Practice Exam, page 210, #6
Answer: C
The difference between work performance information and work performance
data can best be described as:
A. Data is the raw project observations whereas information has been analyzed
through the control processes
B. Data and information are fundamentally the same
C. Information is the raw project observations whereas data has been analyzed
through the control processes
D. Information is an input to data which is an input to the work performance
reports - CORRECT ANSWER Workbook, CAPM Final Practice Exam, page 210, #7
Answer: A
The documented start and finish dates of activities, actual costs and durations,
percent work physically completed would all be considered:
A. Work performance inputs
B. Work performance data
, C. Work performance information
D. Work performance reports - CORRECT ANSWER Workbook, CAPM Final
Practice Exam, page 210, #8
Answer: B
Forecasts, such as budget and schedule forecasts, would be considered
A. Work performance information
B. Work performance data
C. Work performance outputs
D. Work performance reports - CORRECT ANSWER Workbook, CAPM Final
Practice Exam, page 211, #9
Answer: A
Forecasts are considered work performance information as it is project data that
has been analyzed through the control schedule and control cost processes.
Which statement is most accurate:
A. Work performance reports precedes work performance data
B. Work performance data precedes work performance information
C. Work performance information precedes work performance data
D. Work performance reports and information are integrated into work
performance data - CORRECT ANSWER Workbook, CAPM Final Practice Exam,
page 211, #10
Answer: B