, Question 1 - 10 marks
1. What is the correct order of the project phases? (1)
A. Development, Conceptual, Implementation and Termination.
B. Conceptual, Development, Implementation and Termination.
C. Conceptual, Termination, Implementation and Development.
D. Implementation, Termination, Conceptual and Development.
2. Which of the following is not one of the three key project management (1)
functions?
A. Time
B. Cost
C. Resources
D. Quality
3. What is the primary difference between projects and operations? (1)
A. Operations are continuous and repetitive whereas projects are continuous
and unique.
B. Projects are continuous and repetitive whereas operations are temporary
and unique.
C. Operations have yearly planning cycles whereas projects do not require
yearly planning.
D. Operations have more emphasis on roles whereas projects have more
emphasis on goals.
4. Which of the following is not a function of time management? (1)
A. Planning
B. Estimating
C. Scheduling
D. Control
E. C and D
F. None of the above
5. Which of the following is a function of cost management? (1)
A. Estimating
B. Budgeting
C. Control
D. A and B only
E. All of the above
F. None of the above
6. Which of the following contractual factors has no effect on the decision to (1)
tender?
EMC22B1& MCV22B1/ Test 2 MEMO/ May 2019
Page 2
CLASS TEST 2 MEMO:
MAY 2019
SUBJECT : MANAGEMENT II
SUBJECT CODE : EMC22B1 & MCV22B1
EXAMINER : M. L. NDOLOSHE
EMC22B1& MCV22B1/ Test 2 MEMO/ May 2019
Page 1
, Question 1 - 10 marks
1. What is the correct order of the project phases? (1)
A. Development, Conceptual, Implementation and Termination.
B. Conceptual, Development, Implementation and Termination.
C. Conceptual, Termination, Implementation and Development.
D. Implementation, Termination, Conceptual and Development.
2. Which of the following is not one of the three key project management (1)
functions?
A. Time
B. Cost
C. Resources
D. Quality
3. What is the primary difference between projects and operations? (1)
A. Operations are continuous and repetitive whereas projects are continuous
and unique.
B. Projects are continuous and repetitive whereas operations are temporary
and unique.
C. Operations have yearly planning cycles whereas projects do not require
yearly planning.
D. Operations have more emphasis on roles whereas projects have more
emphasis on goals.
4. Which of the following is not a function of time management? (1)
A. Planning
B. Estimating
C. Scheduling
D. Control
E. C and D
F. None of the above
5. Which of the following is a function of cost management? (1)
A. Estimating
B. Budgeting
C. Control
D. A and B only
E. All of the above
F. None of the above
6. Which of the following contractual factors has no effect on the decision to (1)
tender?