MAY / JUNE 2016 EXAM REVISION 1
Please attempt the INF3708 exercises as part of your exam revision. Note that the revision
of assignments & past exam papers are also very crucial for better performance. In fact,
proper understanding of the assignments & past exam papers almost guarantees a pass.


QUESTION 1:
The table below gives the estimated cash flow for three different projects (in rands R):
Year Project 1 Project 2 Project 3
0 - R 195 000 - R 160 000 - R 295 000
1 + R 15 000 + R 15 000 + R 30 000
2 + R 30 000 + R 15 000 + R 35 000
3 + R 55 000 + R 20 000 + R 50 000
4 + R 50 000 + R 35 000 + R 120 000
5 + R 55 000 + R 55 000 + R 110 000
6 + R 50 000 + R 90 000 + R 115 000

1. Calculate the Net Profit of each project. (3)
2. Based on your calculation of the Net Profit, identify which project you would
select to develop. Motivate your answer. (2)
3. Calculate of Return on Investment (ROI) of each of the projects given in the
table above. (3)
4. Based on your calculation of the ROI, identify which project you would
select to develop. (2)


QUESTION 2:
Consider the following project scenario and some questions related to it. The table below gives
the estimated cash flow for three different projects (in South African rands R):
Year Project 1 Project 2 Project 3
0 - R 170 000 - R 150 000 - R 280 000
1 - R 10 000 + R 5 000 + R 10 000
2 + R 20 000 + R 20 000 + R 30 000
3 + R 50 000 + R 30 000 + R 50 000
4 + R 50 000 + R 80 000 + R 120 000
5 + R 60 000 + R 90 000 + R 120 000
6 + R 60 000 - R 10 000 + R 120 000

1. Calculate the Net Profit of each project. (3)
2. Based on your calculation of the Net Profit, identify which project you would
select to develop. Motivate your answer. (2)
3. Calculate of Return on Investment (ROI) of each of the projects given in the
table above. (3)
4. Based on your calculation of the ROI, identify which project you would

, select to develop.(2)
2


QUESTION 3:
1. Consider the following list of tasks with dependencies and estimated durations reflected
in table Draw a CPM network (activity-on-arrow diagram) to illustrate the interaction
of activities. Include all the values in the nodes. Indicate the critical path on the diagram
Task Precedents Duration (weeks)
A - 4 2. Write down the critical path(s)
B - 3 using the letters of the tasks and
C A, B 5 calculate and write down the duration
D - 1 of the project. How many paths are
E C 5 there in total? Identify them all and
F D 2 write them down.
G E, F 5
H G 6


QUESTION 4:
1. Draw a complete Activity-on-arrow network diagram. Include the event number,
earliest date, latest date and slack on each node by completing both a forward and
backward pass. Clearly indicate the total duration and critical path.
Task Precedents Duration (days)
A None 8
B None 10
C None 8
D A 10
E A 16
F D, B 17
G C 18
H C 14
I F, G 9


QUESTION 5:
1. Draw a CPM network for the list of tasks in the table above to illustrate the interaction
of activities. Clearly identify the critical path and its duration.
Activity Precedents Duration (weeks)
A None 7
B A 10
C A 12
D B 3
E B 8
F B 7
G F 2
H D, E 5
I C 13
J C 6
K H 14
L E, F 5

,3

QUESTION 6:
1. Consider the following list of tasks with dependencies and estimated durations reflected
in table Draw a CPM network (activity-on-arrow diagram) to illustrate the interaction
of activities. Include all the values in the nodes. Indicate the critical path on the diagram
Task Precedents Duration (weeks)
A None 6
B None 2
C A 3
D B 2
E C 4
F D 1
G E, F 1
H G 6
I H 3
J H 1
K I, J 1
2. Write down the critical path(s) using the letters of the tasks and calculate and write
down the duration of the project. How many paths are there in total? Identify them all
and write them down.


QUESTION 7:
1. Consider the following activities with their precedents and durations. Draw a complete
Activity-on-arrow network diagram. Include the event number, earliest date, latest
date and slack on each node by completing both a forward and backward pass. Clearly
indicate the total duration and critical path.

Activity Precedents Duration (weeks)
A None 3
B A 4
C B 3
D B 10
E D 8
F D 4
G D 6
H C, E, F, G 8
I H 5
J H 5
K I 4
L J 2
M K, L 4

, 4

QUESTION 8:
Consider the network diagram below indicating the most likely duration of each activity. The
table gives the optimistic and pessimistic durations as well.




OPTIMISTIC MOST PESSIMISTIC EXPECTED STANDARD
(a) LIKELY (m) (b) (te) DEVIATION (s)
A 2 6 10
B 4 5 9
C 7 8 9
D 2 4 12
E 4 6 8
F 3 4 11
G 4 8 9
H 2 2 5



Suppose we must complete the project within 20 weeks and suppose activity D must
be completed by week 12 as the staff member is scheduled on another project after
week 12. Use the table and calculate the following:

1. Calculate the Expected (te) values and Standard Deviation (s) for all the
activities as well as for all the events and indicate all the (te) and (s) values
on the diagram. (10)
2. Draw the PERT network to present this information. (4)
3. Calculate the Z values of event 4 as well as the last event. (4)
4. According to Figure 7.8 (p.181) in your textbook or Figure 2 (question 9 below),
what is the probability of not meeting the final target date for the total project? (2)

Documentinformatie

Geüpload op
5 oktober 2023
Aantal pagina's
158
Geschreven in
2023/2024
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden
$5.50

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
AIMHigher
2.9
(14)
Verkocht
126
Volgers
77
Items
2704
Laatst verkocht
5 maanden geleden



Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen