constitute the Sprint Backlog and are often estimated in hours. -
answerTasks
is responsible for the Scrum process, facilitate the team and
protect the team from outside noise. - answerScrum Master
A Development Teams Daily Scrum is consistently taking longer than 15
minutes. Which Statement best describes what should be done? - answerThe
Scrum Master should facilitate the event in a way that keeps it to the time box.
A new developer is having continuing conflicts with existing Development Team
members and creating a hostile environment. If necessary, who is responsible for
removing the team member? - answerThe Scrum Master is responsible, because
he/she removes impediments. (The ANSWER is actually development team)
A product backlog is never complete - answerTrue - As long as a product
exists, its Product backlog also exists
A Product Owner has the authority to replace an item in the Sprint Backlog -
answerFalse
A properly functioning Scrum Team will have at least one Release Sprint and
may well have several. - answerFalse
A Scrum Master is introducing Scrum to a new Development Team. The Team has
decided that a retrospective is unnecessary. What action should the Scrum Master
take? - answerConsult with the Product Owner to see how he/she feels about the
situation
A Scrum Master is keeping a list of open impediments, but it is growing and he/she
has been able to resolve only a small portion of the impediments. Which three (3)
techniques would be most helpful in this situation? (Choose three answers) -
answer1) Prioritize the list and work on them in
,order
2)Consult with the Development Team
3)Alert management to the impediments and their impacts
A Scrum Master is working with a Development Tea m that has members in different
physical locations. The Development
Team meets in a variety of meeting rooms and has much to do logistically (for
example, set up conference calls) before the Daily Scrum. What action should the
Scrum Master take? - answerSet up the meeting and tell the Development Team
that is how it will be done
A Scrum Master is working with a Development Team that has members in
different physical locations. The Development Team meets in a variety of meeting
rooms and has much to do logistically (for example, set up conference calls) before
the Daily Scrum. What action should the Scrum Master take? - answerAllow the
Development Team to self-manage and determine for itself what to do
A Scrum Team is only allowed to meet with stakeholders during Sprint Review -
answerFalse
A scrum team uses 2 weeks sprints and time box their Sprint Planning to 6 hours.
Does this break rules of Scrum? - answerFalse
According to Scrum, the amount of time for a team to plan Sprint activities is
expressed in what unit of time? - answerHours
According to Scrum, the amount of time for a team to plan Sprint activities is
expressed in what unit of time? - answerHours
All Development Teams working on the same Product should use the same
Product Backlog. - answerTrue
,All the Scrum Teams working on the same product should have the same
Sprint length. - answerFalse
An abnormal termination of a Sprint is called when? - answerWhen the
Product Owner determines that it makes no sense to finish it.
An organization has decided to adopt Scrum, but management wants to change
the terminology to fit with terminology already used. What will likely happen if
this is done? - answerAll answers apply.
1) Without a new vocabulary as a reminder of the change, very little change may
actually happen.
2)The organization may not understand what has changed with Scrum and the
benefits of Scrum may be lost.
3)Management may feel less anxious
As the Sprint Planning meeting progresses, the workload is getting greater than the
Development Team's capacity. Which two actions make the most sense to do?
(Choose 2 answers) - answer1) Remove or change Product Backlog items
2) The Development Team ensures that the Product Owner is aware, starts the
Sprint and monitor progress.
Choose three responsibilities of a self-organizing Development Team. (Choose
three answers) - answer1)Do the work planned in the Sprint Backlog.
2) Pull Product Backlog items for the Sprint.
3) Set the time for the Daily Scrum OR Track Velocity
Could the Sprint Planning be finished if only work planned for the first days of
the Sprint is decomposed to units of one day or less? - answerYes, if the
remaining work is also estimated, maybe in bigger units
Could the Sprint Planning be finished if only work planned for the first days of the
Sprint is decomposed to units of one day or less? - answerYes, if the remaining work
is also estimated,
, maybe in bigger units
Cross-functional teams are optimized to work on a technical layer of a system (e.g.
GUI, database, middle tier, interfaces). - answerFalse
Definition of "Done" is created during the first Sprint and remains unchanged
until the Product release. - answerFalse
Definition of Done can be reviewed and adapted during each Sprint Retrospective.
True or False? - answerTrue
Development Team membership should change: - answerAs needed, while taking
into account a short term reduction in productivity.
Development Teams include which role(s)? - answerNo other roles. Development
Team is a role. A Development Team includes Development Team members
Development teams should be set stretch goals by the Product Owner as part of
Sprint Planning - answerFalse
During a Sprint Retrospective, for what is the Scrum Master responsible? -
answerFacilitating and also participating as a Scrum Team member
During a Sprint, a Development Team determines that it will not be able to finish
the complete forecast. Who should be present to review and adjust the Sprint
work selected? - answerThe Product Owner and the Development Team
During a Sprint, when is new work or further decomposition of work added to the
Sprint Backlog?
- answerAs soon as possible after they are identified