INF3708 – Software Project Management
Chapter 6
Activity planning

6.1 Introduction

A detailed plan for the project, however, must also include a schedule indicating the start and
completion times for each activity. This will enable us to:
 Ensure that the appropriate resources will be available precisely when required;
 Avoid different activities competing for the same time;
 Produce a detailed schedule showing which staffs carry out each activity;
 Produce a detailed plan against which actual achievement may be measured;
 Produce a timed cash flow forecast;
 Re-plan the project during its life to correct drift from the target.


6.2 The objectives of activity planning

In addition to providing project and resource schedules, activity planning aims to achieve a number
of other objectives which may be summarized as follows.
 Feasibility assessment – Is the project possible within required timescales and resource
constraints?
 Resource allocation – What are the most effective ways of allocating resources to the
project.
 Detailed costing – How much will the project cost and when is that expenditure likely to
take place?
 Motivation – Providing targets and being seen to monitor achievement against targets is an
effective way of motivating staff, particularly where they have been involved in setting those
targets in the first place.
 Coordination – When do the staff in different departments need to be available to work on a
particular project and when do staff need to be transferred between projects?

6.3 When to plan

Planning is an ongoing process of refinement, each iteration becoming more detailed and more
accurate than the last. Over successive iterations, the emphasis and purpose of planning will shift.
During the feasibility study arid project start-up, the main purpose of planning will be to estimate
timescales and the risks of not achieving target completion dates or keeping within budget. As the
project proceeds beyond the feasibility study, the emphasis will be placed upon the production of
activity plans for ensuring resource availability and cash flow control.
Throughout the project, until the final deliverable has reached the customer, monitoring and
replanning must continue to correct any drift that might prevent meeting time or cost targets.

6.4 Project schedules

Before work commences on a project or, possibly a stage of a larger project, the project plan must
be developed to the level of showing dates when each activity should start and finish and when and
how much of each resource will be required. Once the plan has been relined to this level of detail we
call it a project schedule. Creating a project schedule comprises four main stages.
The first step in producing the plan is to decide what activities need to be carried out and in
what order they are to be done. From this e can construct an ideal activity plan — that ¡s, a plan of
when each activity would ideally be undertaken were resources not a constraint.

Connected book
 image
Bob Hughes, Mike Cotterell Software Project Management
Publisher: april 2009 ISBN: 9780077122799 Edition: Unknown

Document information

Summarized whole book?
No
Which chapters are summarized?
6
Uploaded on
October 8, 2016
Number of pages
11
Written in
2016/2017
Type
Summary
$3.22

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
khemi
4.0
(23)
Sold
24
Followers
19
Items
14
Last sold
5 year ago

Reviews from verified buyers




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions