MGMT 404 Week 6 Discussion Question
Identify the risk you might encounter in the execution of the task describe the root cause of the risk and the risk impact on the project objectives one of these • Task WBS index: 1.4.3 • Task name: Transfer data • Risk identified: Network capacity • Risk root cause description: Failure during uploads due to low bandwidth • Risk impact: Project delays and budget overrun • Risk owner: Network services What is the purpose of predecessors in the WBS and how are they related to the Identify Risks Pro