• Verkeerd document? Gratis ruilen
  • Geschreven door studenten die geslaagd zijn
  • Direct beschikbaar na je betaling
  • Online lezen of als PDF
Verkopen
Kies je studieland
Kies je taal
Document preview thumbnail
Voorbeeld 2 van de 7 pagina's
Samenvatting

Summary contract law

Document preview thumbnail
Voorbeeld 2 van de 7 pagina's

discharge of contract

Voorbeeld van de inhoud

DISCHARGE OF CONTRACT

There are four ways in which contracts may be discharged:

1. by performance
2. by agreement
3. by breach
4. by frustration


Meaning of ‘discharged’

The above list describes the circumstances in which a party to a contract may be discharged
from their obligations under it.


1 Discharge by performance

General rule: performance must be strict and complete:

Cutter v Powell (1795) 6 Term Rep 320: D agreed to pay C as second mate on a ship bound
from Jamaica to Liverpool. 19 days short of Liverpool C died. Held: C’s widow could not
claim a proportion of the agreed sum. The contract was for sailing to Liverpool and C had
not done so.

Bolton v Mahadevera [1972] 1 WLR 1009: Cl contracted to install central heating into D’s
house. The system was installed but worked very ineffectively and D refused to pay. Held:
the contract had not been performed and Cl could recover nothing.

In each of these (and many other) cases one party is left with a partial performance and
benefit but with no liability to pay at all. Unsurprisingly therefore the courts have been
imaginative in finding exceptions to the general rule:

i) Severable (divisible) contracts

The obligation in Cutter v Powell was for the entire voyage but contracts can provide for
severable obligations:

The Juliana (1822) 2 Dods.504: the contract here provided for payment at a fixed rate per
month. Held: the obligation was monthly so that for each completed month payment was
due.

ii) Prevention of performance

Planché v Colburn (1831) 8 Bing 14: Cl agreed to write a book to be published by D as part of
a series. Cl was to be paid £100 on completion of the book. He collected material and wrote

1

, part of the book and D then cancelled the series. Held: Cl was entitled to be paid for the
work so far done. D had prevented Cl’s further performance and it did not matter whether
the contract was entire or severable.

iii) Acceptance of partial performance

If the contracting party freely accepts partial performance there will be an obligation to pay
for it:

Sumpter v Hedges [1898] 1 QB 673: Cl agreed to build two houses on D’s land for a price of
£565. He did work to the value of £333 and then abandoned the contract, leaving some
materials on site. Held: Cl could recover nothing for the work done as it was an entire
contract but D had voluntarily decided to complete the work using Cl’s materials left on site
and therefore Cl could recover for those materials.

iv) Substantial performance

If the court accepts that there has been substantial performance then there will be a liability
to pay for that performance subject to a claim in damages for the shortfall.

Hoenig v Isaacs [1952] 2 All ER 176: Cl agreed to redecorate and furnish D’s flat for £750. D
complained of faulty design and workmanship and paid only £400. Held: the defects would
cost £55 to correct. There had been substantial performance and Cl was entitled to the
contract price subject to a claim for £55.

2. Discharge by agreement

The parties to a contract can by agreement bring about its discharge. This might occur
because the parties wish to replace the contract with a different one or it may simply be
they wish to walk away from the agreement. The basis is that in each agreeing to give up
whatever rights they had under the contract they are providing each other with
consideration for the discharge which is, therefore, binding.

Forde v Birmingham City Council [2008] EWHC 90105 (Costs) A solicitor was acting on a
conditional fee agreement which it later was thought might be invalid. The solicitor and
client then entered into a second conditional fee agreement that was retrospective to cover
all the work done already as well as future work. Held: the second CFA was valid.


3. Discharge by breach

The breach of contract does not itself discharge or terminate the contract. It is the
acceptance of the breach by the innocent party that enables the contract to be discharged.
The innocent party can only treat the contract as discharged if there has been a breach of
condition or a serious breach of an innominate term. Such a breach is called a repudiatory
breach – it entitles the innocent party to repudiate the contract. The innocent party does
not have to accept the breach and repudiate but they may do so. They can sue in damages

2

Documentinformatie

Studie
Geüpload op
17 december 2021
Aantal pagina's
7
Geschreven in
2019/2020
Type
Samenvatting
$11.02

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Verkocht
0
Volgers
0
Items
90
Laatst verkocht
-



Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen