100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

MECHANIC 102 The Managerial Process ANSWER KEY SOLVED Chapter 6 (MECHANIC102)

Rating
-
Sold
-
Pages
37
Grade
A+
Uploaded on
14-12-2021
Written in
2021/2022

Exam (elaborations) MECHANIC 102 The Managerial Process ANSWER KEY SOLVED Chapter 6 (MECHANIC102) Chapter 06 Developing a Project Plan Answer Key Multiple Choice Questions 1. Information to develop a project network is collected from the A. Organization breakdown structure B. Work breakdown structure C. Budget D. Project proposal E. Responsibility matrix The network is developed from the information collected for the WBS and is a graphic flow chart of the project job plan. AACSB: Reflective Thinking Bloom's: Comprehension Learning Objective: Developing the Project Network Level: Easy 2. Which of the following represents an activity on an AON project network? A. An arrow B. A line C. A node D. Both A and B are correct E. A, B, and C are all correct The two approaches used to develop project networks are known as activity-on-node (AON) and activity-on-arrow (AOA). Both methods use two building blocks— the arrow and the node. Their names derive from the fact that the former uses a node to depict an activity. AACSB: Reflective Thinking Bloom's: Knowledge Learning Objective: Constructing a Project Network Level: Easy 6-1 MECHANIC 102 The Managerial Process ANSWER KEY SOLVED Chapter 6 Developing a Project Plan Chapter 06 - Developing a Project Plan 3. Arrows on an AON project network represent: A. An activity B. Project flow C. Dependency D. Both B and C are correct E. Both A and B are correct The node depicts an activity, and the arrow shows dependency and project flow. AACSB: Reflective Thinking Bloom's: Knowledge Learning Objective: From Work Package to Network Level: Medium 4. When translated into a project network, a work package will become A. A single activity B. One or more activities C. A milestone D. A critical path E. An arrow Work packages from the WBS are used to build the activities found in the project network. An activity can include one or more work packages. The activities are placed in a sequence that provides for orderly completion of the project. AACSB: Analytic Bloom's: Comprehension Learning Objective: From Work Package to Network Level: Medium 6-2 Chapter 06 - Developing a Project Plan 5. Which of the following is provided by a project network but not by the work breakdown structure? A. Dependencies B. Sequencing C. Interrelationships D. Both A and B are correct E. A, B, and C are all correct Project networks are developed from the WBS. The project network is a visual flow diagram of the sequence, interrelationships, and dependencies of all the activities that must be accomplished to complete the project. AACSB: Reflective Thinking Bloom's: Knowledge Learning Objective: From Work Package to Network Level: Medium 6. On a project network, the activity times are derived from the A. Organization breakdown structure B. Work packages C. Budget D. Project proposal E. Responsibility matrix Work packages from the WBS are used to build the activities found in the project network. An activity is an element in the project that consumes time—for example, work or waiting. AACSB: Analytic Bloom's: Comprehension Learning Objective: From Work Package to Network Level: Difficult 6-3 Chapter 06 - Developing a Project Plan 7. Part of a project is to Develop Product Specifications. This is best classified as a(n) A. Event B. Path C. Activity D. Node E. Milestone Activities usually represent one or more tasks from a work package. Descriptions of activities should use a verb/noun format: for example, develop product specifications. AACSB: Analytic Bloom's: Knowledge Learning Objective: Constructing a Project Network Level: Medium 8. An activity that has more than one dependency arrow flowing into it is termed a(n) A. Parallel activity B. Critical path C. Burst activity D. Merge activity E. Independent activity Merge activity is an activity that has more than one activity immediately preceding it (more than one dependency arrow flowing to it). AACSB: Reflective Thinking Bloom's: Knowledge Learning Objective: Constructing a Project Network Level: Easy 6-4 Chapter 06 - Developing a Project Plan 9. The critical path in a project network is the A. Shortest path through the network B. Longest path through the network C. Network path with the most difficult activities D. Network path using the most resources E. Network path with the most merge activities When this term is used, it means the path(s) with the longest duration through the network; if an activity on the path is delayed, the project is delayed the same amount of time. AACSB: Reflective Thinking Bloom's: Comprehension Learning Objective: Constructing a Project Network Level: Medium 10. A/an _________ activity has more than one dependency arrow flowing from it. A. Parallel B. Critical path C. Burst D. Merge E. Independent Burst activity is an activity has more than one activity immediately following it (more than one dependency arrow flowing from it). AACSB: Analytic Bloom's: Comprehension Learning Objective: Constructing a Project Network Level: Easy 6-5 Chapter 06 - Developing a Project Plan 11. An item on a project network is Design Software Completed. This is best described as a(n) A. Event B. Path C. Activity D. Node E. Milestone Event is a term used to represent a point in time when an activity is started or completed. It does not consume time. AACSB: Reflective Thinking Bloom's: Knowledge Learning Objective: Constructing a Project Network Level: Easy 12. Activities which can take place at the same time are termed A. Parallel activity B. Critical path C. Burst activity D. Merge activity E. Independent activity These are activities that can take place at the same time, if the manager wishes. However, the manager may choose to have parallel activities not occur simultaneously. AACSB: Analytic Bloom's: Knowledge Learning Objective: Constructing a Project Network Level: Easy 6-6 Chapter 06 - Developing a Project Plan 13. A sequence of connected, dependent activities is termed a(n) A. Critical path B. Parallel path C. Activity chain D. Path E. Dependent chain A Path is a sequence of connected, dependent activities. AACSB: Reflective Thinking Bloom's: Knowledge Learning Objective: Constructing a Project Network Level: Easy 14. An AON project network uses which of the following basic building blocks? A. Arrows B. Bars C. Nodes D. Both A and C are correct E. A, B, and C are all correct The two approaches used to develop project networks are known as activity-on-node (AON) and activity-on-arrow (AOA). Both methods use two building

Show more Read less











Whoops! We can’t load your doc right now. Try again or contact support.

Document information

Uploaded on
December 14, 2021
Number of pages
37
Written in
2021/2022
Type
Exam (elaborations)
Contains
Questions & answers

Content preview

MECHANIC 102 The Managerial
Process ANSWER KEY SOLVED Chapter
Chapter 06 - Developing a Project Plan

6 Developing a Project Plan
Chapter 06 Developing a Project Plan Answer Key



Multiple Choice Questions



1. Information to develop a project network is collected from the
A. Organization breakdown structure
B. Work breakdown structure
C. Budget
D. Project proposal
E. Responsibility matrix

The network is developed from the information collected for the WBS and is a graphic flow
chart of the project job plan.


AACSB: Reflective Thinking
Bloom's: Comprehension
Learning Objective: Developing the Project Network
Level: Easy



2. Which of the following represents an activity on an AON project network?
A. An arrow
B. A line
C. A node
D. Both A and B are correct
E. A, B, and C are all correct

The two approaches used to develop project networks are known as activity-on-node (AON)
and activity-on-arrow (AOA). Both methods use two building blocks— the arrow and the
node. Their names derive from the fact that the former uses a node to depict an activity.


AACSB: Reflective Thinking
Bloom's: Knowledge
Learning Objective: Constructing a Project Network
Level: Easy




6-1

,Chapter 06 - Developing a Project Plan



3. Arrows on an AON project network represent:
A. An activity
B. Project flow
C. Dependency
D. Both B and C are correct
E. Both A and B are correct

The node depicts an activity, and the arrow shows dependency and project flow.


AACSB: Reflective Thinking
Bloom's: Knowledge
Learning Objective: From Work Package to Network
Level: Medium



4. When translated into a project network, a work package will become
A. A single activity
B. One or more activities
C. A milestone
D. A critical path
E. An arrow

Work packages from the WBS are used to build the activities found in the project network.
An activity can include one or more work packages. The activities are placed in a sequence
that provides for orderly completion of the project.


AACSB: Analytic
Bloom's: Comprehension
Learning Objective: From Work Package to Network
Level: Medium




6-2

,Chapter 06 - Developing a Project Plan



5. Which of the following is provided by a project network but not by the work breakdown
structure?
A. Dependencies
B. Sequencing
C. Interrelationships
D. Both A and B are correct
E. A, B, and C are all correct

Project networks are developed from the WBS. The project network is a visual flow diagram
of the sequence, interrelationships, and dependencies of all the activities that must be
accomplished to complete the project.


AACSB: Reflective Thinking
Bloom's: Knowledge
Learning Objective: From Work Package to Network
Level: Medium



6. On a project network, the activity times are derived from the
A. Organization breakdown structure
B. Work packages
C. Budget
D. Project proposal
E. Responsibility matrix

Work packages from the WBS are used to build the activities found in the project network.
An activity is an element in the project that consumes time—for example, work or waiting.


AACSB: Analytic
Bloom's: Comprehension
Learning Objective: From Work Package to Network
Level: Difficult




6-3

, Chapter 06 - Developing a Project Plan



7. Part of a project is to Develop Product Specifications. This is best classified as a(n)
A. Event
B. Path
C. Activity
D. Node
E. Milestone

Activities usually represent one or more tasks from a work package. Descriptions of activities
should use a verb/noun format: for example, develop product specifications.


AACSB: Analytic
Bloom's: Knowledge
Learning Objective: Constructing a Project Network
Level: Medium



8. An activity that has more than one dependency arrow flowing into it is termed a(n)
A. Parallel activity
B. Critical path
C. Burst activity
D. Merge activity
E. Independent activity

Merge activity is an activity that has more than one activity immediately preceding it (more
than one dependency arrow flowing to it).


AACSB: Reflective Thinking
Bloom's: Knowledge
Learning Objective: Constructing a Project Network
Level: Easy




6-4

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Expert001 Chamberlain School Of Nursing
View profile
Follow You need to be logged in order to follow users or courses
Sold
798
Member since
4 year
Number of followers
566
Documents
1190
Last sold
2 days ago
Expert001

High quality, well written Test Banks, Guides, Solution Manuals and Exams to enhance your learning potential and take your grades to new heights. Kindly leave a review and suggestions. We do take pride in our high-quality services and we are always ready to support all clients.

4.2

159 reviews

5
104
4
18
3
14
2
7
1
16

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions