PMP QUESTIONS AND
ANSWERS #2
,Classified
PMP Questions and Answers #2
During a team meeting, a team member asks about the
measurements that will be used on the project to judge
performance. The team member feels that some of the measures
related to the activities assigned to him are not valid measurements.
The project is BEST considered in what part of the project
management process?
A-)
Initiating
B-)
Executing
C-) Monitoring &
Controlling D-) Closing
The answer is B. Executing. The question states that team member
feels some of the measures on his activities are not valid. Therefore,
he must be working during the executing phase of the project where
project deliverables are produced and project members perform
most of their assigned work.
Knowledge Area: Project Management Processes
PMP Questions and Answers #3
Your company just won a major new project. It will begin in three
months and is valued at $2m USD. You are the project manager for
an existing project.
What is the FIRST thing you should do once you hear of the
new project? A-) Ask management how the new project will use
resources
B-) Resource level your
project C-) Crash your
,Classified
project
D-) Ask management how the new project will affect your project
The answer is D. Ask management how the new project will affect
your project. Since this is another project that your company is
going to execute, you need to determine whether it will impact
your project.
, Classified
Knowledge Area: Integration Management Knowledge Area
PMP Questions and Answers #4
You are a new project manager who has never managed a
project before. It would be BEST in this situation to rely on
during planning in
order to improve your chance of success.
A-) Your intuition and
training B-) Stakeholder
analysis
C-) Historical information
D-) Configuration management
The answer is C. Historical information. The first thing to explore
before starting a new project is the historical information about
similar projects in the organizational process assets library of the
organization.
Knowledge Area: Integration Management Knowledge Area
PMP Questions and Answers #5
During project executing, a team member comes to the project
manager because he is not sure of what work he needs to
accomplish on the project. Which of the following documents
contain detailed descriptions of work packages?
A-) WBS
Dictionary B-)
Activity List
ANSWERS #2
,Classified
PMP Questions and Answers #2
During a team meeting, a team member asks about the
measurements that will be used on the project to judge
performance. The team member feels that some of the measures
related to the activities assigned to him are not valid measurements.
The project is BEST considered in what part of the project
management process?
A-)
Initiating
B-)
Executing
C-) Monitoring &
Controlling D-) Closing
The answer is B. Executing. The question states that team member
feels some of the measures on his activities are not valid. Therefore,
he must be working during the executing phase of the project where
project deliverables are produced and project members perform
most of their assigned work.
Knowledge Area: Project Management Processes
PMP Questions and Answers #3
Your company just won a major new project. It will begin in three
months and is valued at $2m USD. You are the project manager for
an existing project.
What is the FIRST thing you should do once you hear of the
new project? A-) Ask management how the new project will use
resources
B-) Resource level your
project C-) Crash your
,Classified
project
D-) Ask management how the new project will affect your project
The answer is D. Ask management how the new project will affect
your project. Since this is another project that your company is
going to execute, you need to determine whether it will impact
your project.
, Classified
Knowledge Area: Integration Management Knowledge Area
PMP Questions and Answers #4
You are a new project manager who has never managed a
project before. It would be BEST in this situation to rely on
during planning in
order to improve your chance of success.
A-) Your intuition and
training B-) Stakeholder
analysis
C-) Historical information
D-) Configuration management
The answer is C. Historical information. The first thing to explore
before starting a new project is the historical information about
similar projects in the organizational process assets library of the
organization.
Knowledge Area: Integration Management Knowledge Area
PMP Questions and Answers #5
During project executing, a team member comes to the project
manager because he is not sure of what work he needs to
accomplish on the project. Which of the following documents
contain detailed descriptions of work packages?
A-) WBS
Dictionary B-)
Activity List