LSU CM Exit- Exam and All Correct Answers 2026.

Document preview thumbnail
Voorbeeld 2 van de 9 pagina's

Conventional concrete typically weighs ____________ - Answer 140pcf - 150pcf BTU - Answer British Thermal Unit - A quantity of heat. It is the amount of heat needed to raise a pound of water 1°F. An MBH is 1,000 BTUs/hr. Sensible Heat - Answer "Dry Heat" - Heat added to the air without adding moisture. As sensible heat increases the points on the psychrometric chart move to the right. Latent Heat - Answer The hidden heat added to the air by adding moisture (approx. 1,000 BTUs/lb of water). As latent heat increases the points on the psychrometric chart move up. Enthalpy - Answer (h) - is the total amount of thermal energy (sensible & latent) in the air. It is measured in BTUs per lb of dry air. Depreciable value is the purchase price less the __________ - Answer Salvage Value The difference between a current asset and a long term asset is ______________ - Answer Current assets can be liquidated within one year and long term assets cannot Current Ratio - Answer This accounting ratio is calculated by dividing the total current assets by the total current liabilities Working capital of a construction company increases when - Answer A company sells equipment or assets When an owner decides to add additional work to the original scope, this is considered what type of change? - Answer Owner Directed Change Order All of the following are steps that a construction company can follow in applying risk management except one. - Answer Avoid all risky situations. Complete the risk statement...if a/an _______________ happens, then the steel material for the project may cost more than the budget, which will impact the stele subcontractors, causing an increase in the project cost. - Answer Fluctuation in the steel price.

Voorbeeld van de inhoud

LSU CM Exit- Exam and All Correct
Answers 2026.
Conventional concrete typically weighs ____________ - Answer 140pcf - 150pcf



BTU - Answer British Thermal Unit - A quantity of heat. It is the amount of heat needed to
raise a pound of water 1°F. An MBH is 1,000 BTUs/hr.



Sensible Heat - Answer "Dry Heat" - Heat added to the air without adding moisture. As
sensible heat increases the points on the psychrometric chart move to the right.



Latent Heat - Answer The hidden heat added to the air by adding moisture (approx. 1,000
BTUs/lb of water). As latent heat increases the points on the psychrometric chart move up.



Enthalpy - Answer (h) - is the total amount of thermal energy (sensible & latent) in the air. It is
measured in BTUs per lb of dry air.



Depreciable value is the purchase price less the __________ - Answer Salvage Value



The difference between a current asset and a long term asset is ______________ - Answer
Current assets can be liquidated within one year and long term assets cannot



Current Ratio - Answer This accounting ratio is calculated by dividing the total current assets
by the total current liabilities



Working capital of a construction company increases when - Answer A company sells
equipment or assets



When an owner decides to add additional work to the original scope, this is considered what
type of change? - Answer Owner Directed Change Order



All of the following are steps that a construction company can follow in applying risk
management except one. - Answer Avoid all risky situations.



Complete the risk statement...if a/an _______________ happens, then the steel material for the
project may cost more than the budget, which will impact the stele subcontractors, causing an
increase in the project cost. - Answer Fluctuation in the steel price.

, Which of the following best describes risk? - Answer The potential event that results in an
outcome that is different than what's planned.



Typical steps associated with the risk management process are identify the risk, analyze the
identified risks, _____________, allocate risks contractually, and monitor and control risks
throughout the design and construction of a project. - Answer Mitigate and plan to address
risks.



Which of the following is not a risk identification tool and technique that construction managers
use. - Answer Value Engineering



Change Order - Answer A written order to the contractor authorizing changes in work to the
signed original documents (not the bid documents)



An acceptance is ______________________________. - Answer An unconditional agreement
with an offer



What is the constructive acceleration? - Answer It is the forced completion of the contract
work in a shorter period than should have been allowed by the issuance of a warranted time
extension.



What is the cardinal rule of documentation and records? - Answer Put it in writing.



Which one of the following is NOT an alternative dispute resolution method? - Answer
Litigation



__________________ is a sum withheld from progress payments to the contractor in
accordance with the terms of

the contract - Answer Retainage (retention)



Define progress curves. - Answer A display of cumulative costs, labor hours, or other
quantities against time as s-curves.



From the following list, which tool does not help a project manager to control costs on a
project? - Answer Baseline schedules



If a project that is 40% complete has a cost variance of -$45,000, what does this mean? -
Answer The project is currently $45,000 over-budget

Documentinformatie

Geüpload op
19 oktober 2026
Aantal pagina's
9
Geschreven in
2026/2027
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden
$12.49

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
COCOSOLUTIONS
4.1
(39)
Verkocht
235
Volgers
16
Items
9864
Laatst verkocht
5 dagen geleden



Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen