,Q1
Which document defines the functional requirements, expectations, and limitations of a building
project from the owner's perspective?
A) Basis of Design (BOD)
B) Owner's Project Requirements (OPR) CORRECT
C) Commissioning Plan
D) Systems Manual
Rationale
The OPR is the foundational document that captures the owner's intent, functional needs, and
performance expectations for the facility. The BOD translates the OPR into technical design solutions,
while the Commissioning Plan defines how the process will be executed.
Q2
What is the primary purpose of the Basis of Design (BOD)?
A) To document the commissioning budget
B) To translate the Owner's Project Requirements into technical design criteria
CORRECT
and assumptions
C) To list all contractor submittals
D) To establish the construction schedule
Rationale
The BOD documents the design team's approach to meeting the OPR, including system selections,
calculations, and assumptions. It serves as a reference for design review and verification.
Q3
During which phase are the OPR and the initial Commissioning Plan formally accepted by the
owner?
A) Construction Phase
B) Predesign Phase CORRECT
C) Occupancy Phase
2
,D) Warranty Phase
Rationale
ASHRAE Guideline 0 establishes that the OPR and the Cx Plan are developed and formally accepted
during the Predesign Phase, ensuring owner expectations are documented before design begins.
Q4
Which ASHRAE standard provides the minimum acceptable commissioning process
requirements for new buildings and new systems?
A) Guideline 0
B) Standard 202 CORRECT
C) Standard 90.1
D) Guideline 1.1
Rationale
ANSI/ASHRAE/IES Standard 202 identifies the minimum acceptable Commissioning Process for new
buildings and new systems, including activities, documentation, and acceptance requirements.
Q5
What is the primary purpose of a pre-functional checklist?
A) To document that equipment has been installed, started up, and is ready for
CORRECT
functional testing
B) To list the owner's operational preferences
C) To calculate the commissioning budget
D) To schedule training sessions
Rationale
Pre-functional checklists are completed by contractors to verify static conditions such as proper
installation, utility connections, and start-up, ensuring equipment is ready before functional performance
testing begins.
3
, Q6
During functional performance testing (FPT), what is the primary role of the commissioning
provider (CxP)?
A) To operate the equipment as the contractor
B) To witness, document, and verify that system performance meets the OPR
CORRECT
and contract documents
C) To design the control sequences
D) To approve contractor invoices
Rationale
The CxP witnesses and documents FPT to verify that systems perform in accordance with the design
intent and OPR. The contractor typically operates the equipment during testing.
Q7
What is an issues log used for during the commissioning process?
A) To record the budget for each system
B) To track, document, and resolve deficiencies identified during design review,
CORRECT
construction observation, and testing
C) To list the training schedule
D) To record meeting attendance
Rationale
The issues log is a central tracking tool for recording deficiencies, assigning responsibility, and
monitoring resolution throughout the commissioning process.
Q8
Which document outlines the organization, schedule, roles, responsibilities, and procedures for
commissioning a specific project?
A) OPR
B) BOD
C) Commissioning Plan CORRECT
4