1. What is the minimum BTU heat input for a heating system
that requires a Massachusetts pipefitting license?
A) 500,000 BTU
B) 700,000 BTU
C) 1,000,000 BTU
D) 1,500,000 BTU
Correct answer: B
Rationale: Pipefitting is required for heating systems with a
rating greater than 700,000 BTU .
2. What is the minimum amount of supervised work
experience required to obtain a Journeyman Pipefitter
License in Massachusetts?
A) 2,000 hours
B) 4,000 hours
C) 6,000 hours
D) 8,000 hours
Correct answer: C
Rationale: Applicants must have worked not less than 6,000
hours as a Pipefitter Apprentice in Massachusetts .
,3. How many hours of A.S.M.E. Code instruction are
required for the Journeyman Pipefitter License under the
6,000-hour pathway?
A) 100 hours
B) 200 hours
C) 350 hours
D) 500 hours
Correct answer: C
Rationale: Under the 6,000-hour pathway, applicants must
complete 350 hours of A.S.M.E. Code Instruction .
4. What is the minimum passing score for the Massachusetts
Journeyman Pipefitter examination?
A) 60%
B) 65%
C) 70%
D) 75%
Correct answer: C
Rationale: Candidates must correctly answer 70% or more
of the questions to qualify for a license .
5. What is the application processing fee for the
Journeyman Pipefitter License?
A) $40
,B) $75
C) $100
D) $150
Correct answer: B
Rationale: The Journeyman Pipefitter application
processing fee is $75.00 .
6. A professional engineer must design pole scaffolding that
is in excess of how many feet high?
A) 20 feet
B) 30 feet
C) 40 feet
D) 50 feet
Correct answer: B
Rationale: A professional engineer must design pole
scaffolding in excess of 30 feet high .
7. What is the minimum size for gauge glass connections?
A) 1/4"
B) 3/8"
C) 1/2"
D) 3/4"
Correct answer: C
, Rationale: All gauge glass connections shall not be less than
1/2" pipe size .
8. What is the minimum size connection required for a
bottom blow-off?
A) 1/2"
B) 3/4"
C) 1"
D) 1 1/4"
Correct answer: C
Rationale: The bottom blow-off minimum connection size is
1" .
9. What is the maximum size connection allowed for a
bottom blow-off?
A) 1 1/2"
B) 2"
C) 2 1/2"
D) 3"
Correct answer: C
Rationale: The bottom blow-off maximum connection size is
2 1/2" .
10. What is the maximum size connection allowed for a
threaded safety valve?
License Exam | COMPLETE EXAM WITH
ANSWERS AND RATIONALES
1. What is the minimum BTU heat input for a heating system
that requires a Massachusetts pipefitting license?
A) 500,000 BTU
B) 700,000 BTU
C) 1,000,000 BTU
D) 1,500,000 BTU
Correct answer: B
Rationale: Pipefitting is required for heating systems with a
rating greater than 700,000 BTU .
2. What is the minimum amount of supervised work
experience required to obtain a Journeyman Pipefitter
License in Massachusetts?
A) 2,000 hours
B) 4,000 hours
C) 6,000 hours
D) 8,000 hours
Correct answer: C
Rationale: Applicants must have worked not less than 6,000
hours as a Pipefitter Apprentice in Massachusetts .
,3. How many hours of A.S.M.E. Code instruction are
required for the Journeyman Pipefitter License under the
6,000-hour pathway?
A) 100 hours
B) 200 hours
C) 350 hours
D) 500 hours
Correct answer: C
Rationale: Under the 6,000-hour pathway, applicants must
complete 350 hours of A.S.M.E. Code Instruction .
4. What is the minimum passing score for the Massachusetts
Journeyman Pipefitter examination?
A) 60%
B) 65%
C) 70%
D) 75%
Correct answer: C
Rationale: Candidates must correctly answer 70% or more
of the questions to qualify for a license .
5. What is the application processing fee for the
Journeyman Pipefitter License?
A) $40
,B) $75
C) $100
D) $150
Correct answer: B
Rationale: The Journeyman Pipefitter application
processing fee is $75.00 .
6. A professional engineer must design pole scaffolding that
is in excess of how many feet high?
A) 20 feet
B) 30 feet
C) 40 feet
D) 50 feet
Correct answer: B
Rationale: A professional engineer must design pole
scaffolding in excess of 30 feet high .
7. What is the minimum size for gauge glass connections?
A) 1/4"
B) 3/8"
C) 1/2"
D) 3/4"
Correct answer: C
, Rationale: All gauge glass connections shall not be less than
1/2" pipe size .
8. What is the minimum size connection required for a
bottom blow-off?
A) 1/2"
B) 3/4"
C) 1"
D) 1 1/4"
Correct answer: C
Rationale: The bottom blow-off minimum connection size is
1" .
9. What is the maximum size connection allowed for a
bottom blow-off?
A) 1 1/2"
B) 2"
C) 2 1/2"
D) 3"
Correct answer: C
Rationale: The bottom blow-off maximum connection size is
2 1/2" .
10. What is the maximum size connection allowed for a
threaded safety valve?