SECTION 1: FLORIDA LICENSING, BUSINESS LAW, AND REGULATORY COMPLIANCE
Question 1
A contractor holds a state-certified electrical license and is offered a project in a county
where the contractor has no local registration. What is the contractor's legal authority?
A. The contractor must obtain a local competency card before working in that county.
B. The contractor may work statewide without additional local registration.
C. The contractor must form a partnership with a locally registered contractor.
D. The contractor may work only if the project value exceeds $50,000.
Correct Answer: B
Explanation: State-certified electrical contractors possess statewide scope and are not
limited to specific local jurisdictions, unlike registered contractors.
Question 2
A qualifying agent for an electrical contracting corporation leaves the company. What must
the business do to continue lawful electrical contracting operations?
A. Immediately cease all electrical contracting until a new qualifying agent is associated.
B. Have any licensed electrician on staff sign a temporary qualification form.
C. Notify the DBPR within 30 days and continue operations with supervision by a master
electrician.
D. Transfer the license to the corporation's president regardless of licensure status.
,Correct Answer: A
Explanation: A qualifying agent is essential for a business entity's authorization; without
proper qualification, the business cannot lawfully engage in contracting.
Question 3
On a private commercial project, a subcontractor first furnishes materials on March 1. By
what date must the subcontractor serve a Notice to Owner to preserve lien rights?
A. March 15
B. March 31
C. April 15
D. April 30
Correct Answer: C
Explanation: A Notice to Owner must be served within 45 days of first furnishing labor or
materials to preserve lien rights.
Question 4
A Florida certified electrical contractor is renewing a license. Which continuing education
requirement applies?
A. 8 hours every year including 2 hours of code updates.
B. 14 hours per renewal cycle including 1 hour of workers' compensation and 1 hour of
workplace safety.
C. 20 hours per renewal cycle with no specific topic requirements.
D. 10 hours per renewal cycle including 1 hour of business practices.
,Correct Answer: B
Explanation: Florida certified electrical contractors must complete 14 hours of approved
continuing education per renewal cycle with specific required topics.
Question 5
A sole proprietor electrical contractor with no employees wishes to operate without
workers' compensation insurance. What is the contractor's option?
A. The contractor may file an exemption with the state if meeting specific requirements.
B. Workers' compensation is always mandatory regardless of employee count.
C. The contractor may waive coverage by signing a notarized affidavit at the job site.
D. Only corporations may claim workers' compensation exemptions.
Correct Answer: A
Explanation: Sole proprietors with no employees may qualify for a workers' compensation
exemption by filing proper documentation with the state.
Question 6
A homeowner hires an unlicensed individual to perform a $3,000 electrical panel
replacement. What is the legal classification of this activity in Florida?
A. A civil infraction with a warning.
B. A misdemeanor or felony depending on circumstances.
C. Legal because the amount is under $5,000.
D. Legal if the homeowner signs a liability waiver.
, Correct Answer: B
Explanation: Unlicensed electrical contracting in Florida can be charged as a misdemeanor or
felony, with significant penalties including fines and imprisonment.
Question 7
A contractor is preparing to install a new 400-ampere service. What must be obtained before
beginning work?
A. An electrical permit from the local building department.
B. Only a notification to the utility company.
C. A plumbing permit if the service is near water lines.
D. No permit is required for service upgrades.
Correct Answer: A
Explanation: An electrical permit must be obtained from the local authority having
jurisdiction before starting most electrical work, including service installations.
Question 8
A local Florida jurisdiction wishes to adopt stricter electrical safety requirements than the
state minimum code. Is this permitted?
A. No, local jurisdictions must adopt identical code requirements.
B. Yes, local jurisdictions may adopt more stringent amendments.
C. Yes, but only with approval from the Florida Electrical Contractors' Licensing Board.
D. No, less stringent amendments are the only local option.
Correct Answer: B