• Verkeerd document? Gratis ruilen
  • Geschreven door studenten die geslaagd zijn
  • Direct beschikbaar na je betaling
  • Online lezen of als PDF
Verkopen
Kies je studieland
Kies je taal
Document preview thumbnail
Voorbeeld 4 van de 100 pagina's
Tentamen (uitwerkingen)

CAPM Practice Exam 150 Questions Answers Verified Questions with 100 Correct Answers Graded A

Document preview thumbnail
Voorbeeld 4 van de 100 pagina's

CAPM Exam 150 Verified Practice Questions and Answers | Expert-Verified Solutions 5 process groups - answer - Initiating Planning Executing Monitoring and Controlling Closing ten knowledge areas - answer - Integration Scope Time Cost Quality HR Communications Risk Procurement Stakeholder management total float formula - answer - total float = late finish - early finish normal distribution - answer - bell curve - symmetrical distribution - 50% chance of falling below the mean and 50% chance of falling above the mean (1sigma=68.27%. 2sigma = 95.45%. 3sigma= 99.73%) triangular distribution - answer - when there are 3 possible values w/ equal probability - distribution is a triangle. A= lowest value, B= highest value, M = most likely value beta distribution (PERT) - answer - triangular distribution w/ more weight given to the most likely estimate (can be asymmetrical). O = optimistic estimate, ML=most likely estimate, P=pessimistic estimate mean for a beta distribution - answer - mean = (O + 4ML + P)/6 standard deviation for beta distribution - answer - standard deviation = (P-O)/6 statistical sums - answer - project mean is the sum of the means of the individual tasks. project standard deviation is the square root of the project variance earned value management - answer - used to monitor the progress of a project and is an analytical technique. uses 3 independent values - PV, AC, EV planned value (PV) - answer - the budget or the portion of the approved cost estimate planned to be spent during a given period actual cost (AC) - answer - the total of direct and indirect costs incurred in accomplishing work during a given period earned value (EV) - answer - the budget for the work accomplished in a given period cost variance (CV) - answer - CV = EV - AC schedule variance (SV) - answer - SV = EV - PV cost performance index (CPI) - answer - CPI = EV/AC schedule performance index (SPI) - answer - SPI = EV/PV positive CV indicates, negative CV indicates - answer - costs are below budget, costs are overrun positive SV indicates, negative SV indicates - answer - a project is ahead of schedule, a project is behind schedule CPI greater than 1.0 indicates - answer - costs are below budget SPI greater than 1.0 indicates - answer - project is ahead of schedule CPI less than 1.0 indicates - answer - costs are over budget SPI less than 1.0 indicates - answer - a project is behind schedule estimate at completion (EAC) - answer - the amount we expect the total project to cost on completion and as of the "data date" (time now) new estimate technique for finding EAC - answer - EAC = AC/new estimate for remaining work new estimate is most applicable when: - answer - the actual performance to date shows that the original estimates were fundamentally flawed or when they are no longer accurate because of changes in conditions relating to the project original estimate technique for finding EAC - answer - EAC = AC/(BAC - EV) original estimate is most applicable when: - answer - actual variances to date are seen as being the exception, and the expectations for the future are that the original estimates are more reliable than the actual work effort efficiency date performance estimate low technique for finding EAC - answer - EAC = AC + (BAC - EV)/CPI or EAC = BAC/CPI performance estimate low formula is most applicable when: - answer - future variances are projected to approximate the same level as current variances performance estimate high technique for finding EAC - answer - EAC = AC + (BAC - EV) / (CPI)(SPI) performance estimate high formula is most applicable when: - answer - the project is over budget and the schedule impacts the work remaining to be completed BAC - answer - budget at completion. the total budgeted cost of all approved activities ETC - answer - estimate to complete - the estimate for completing the remaining work for a schedu


Documentinformatie

Geüpload op
14 oktober 2026
Aantal pagina's
100
Geschreven in
2026/2027
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden
$12.99

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
SARAHnkalu
4.6
(7)
Verkocht
40
Volgers
0
Items
3467
Laatst verkocht
3 dagen geleden



Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen

Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.