Massachusetts Construction Supervisor License (CSL) Practice Exam
Section 1: Licensing, Codes, and Legal Responsibilities (Questions 1–15)
These questions focus on Massachusetts licensing, permits, code compliance, and the
responsibilities of a construction supervisor.
1. Which organization administers the Massachusetts CSL examination under the current
testing arrangements?
A. OSHA B. PSI C. FEMA D. The local fire department
Correct answer: B. PSI
Rationale: Massachusetts identifies PSI as the examination provider for the 10th Edition CSL
testing program.
Massachusetts Government
2. Which Massachusetts regulation contains the State Building Code?
A. 527 CMR B. 780 CMR C. 248 CMR D. 310 CMR
Correct answer: B. 780 CMR
Rationale: The Massachusetts State Building Code is designated 780 CMR and incorporates
model codes and Massachusetts-specific amendments.
Massachusetts Government
3. What is the minimum passing score stated in the Massachusetts CSL candidate handbook?
A. 50% B. 60% C. 70% D. 80%
Correct answer: C. 70%
Rationale: The candidate handbook states that candidates must score at least 70% to pass an
examination.
Massachusetts Government
4. What is the primary purpose of a Construction Supervisor License?
, 2
A. To authorize electrical wiring without restrictions B. To establish qualification to supervise
construction work within the license's scope C. To replace all building permits D. To authorize
plumbing work automatically
Correct answer: B. To establish qualification to supervise construction work within the
license's scope
Rationale: A CSL qualifies an individual to supervise covered construction activities within
the applicable license category. It does not replace other trade licenses or permit
requirements.
Massachusetts Government
5. Which license category generally covers buildings of any use containing less than 35,000
cubic feet, as well as specified other structures?
A. Unrestricted CSL B. Electrical contractor license C. Plumbing license D. Demolition-only
permit
Correct answer: A. Unrestricted CSL
Rationale: Massachusetts describes the unrestricted license as covering specified
construction work, including buildings of any use below the stated enclosed-volume
threshold. The full scope and exceptions must be checked in the regulations.
Massachusetts Government
6. Which code edition is the basis of the current Massachusetts CSL examination program
that began in 2025?
A. Fifth Edition B. Seventh Edition C. Ninth Edition D. Tenth Edition
Correct answer: D. Tenth Edition
Rationale: Massachusetts transitioned CSL testing to the 10th Edition of the State Building
Code on January 1, 2025.
Massachusetts Government
7. What should a supervisor do if the approved construction drawings conflict with actual
site conditions?
, 3
A. Ignore the drawings B. Make any change without informing anyone C. Stop the affected
work and seek clarification through the appropriate design and approval process D. Cover
the discrepancy with finishes
Correct answer: C. Stop the affected work and seek clarification through the appropriate
design and approval process
Rationale: Unresolved discrepancies can affect structural integrity, code compliance, and
safety. Clarification should be obtained before proceeding with the affected work.
8. Who is responsible for determining whether a building permit is required for a proposed
project?
A. Only the material supplier B. The project team must comply with applicable permit rules
and confirm requirements with the local building official C. Only the homeowner's neighbor
D. The concrete delivery driver
Correct answer: B. The project team must comply with applicable permit rules and confirm
requirements with the local building official
Rationale: Permit requirements depend on the project and applicable regulations. The local
building department can clarify local requirements and the appropriate approval process.
9. What is the purpose of a building inspection?
A. To guarantee that a building will never fail B. To assess compliance with applicable code
requirements at the relevant construction stage C. To replace the contractor's quality-control
program D. To set the contractor's prices
Correct answer: B. To assess compliance with applicable code requirements at the relevant
construction stage
Rationale: Inspections help verify compliance with building requirements. They do not
eliminate the contractor's responsibility for workmanship, safety, and quality.
10. What should a supervisor do when an inspector identifies a code violation?
A. Conceal the violation B. Continue the affected work without review C. Understand the
violation, correct it as required, and arrange any necessary reinspection D. Remove the
inspection record
Correct answer: C. Understand the violation, correct it as required, and arrange any
necessary reinspection
Rationale: Correcting documented deficiencies and following the required approval process
helps establish compliance.
11. Why should construction drawings and specifications be available on site?
Massachusetts Construction Supervisor License (CSL) Practice Exam
Section 1: Licensing, Codes, and Legal Responsibilities (Questions 1–15)
These questions focus on Massachusetts licensing, permits, code compliance, and the
responsibilities of a construction supervisor.
1. Which organization administers the Massachusetts CSL examination under the current
testing arrangements?
A. OSHA B. PSI C. FEMA D. The local fire department
Correct answer: B. PSI
Rationale: Massachusetts identifies PSI as the examination provider for the 10th Edition CSL
testing program.
Massachusetts Government
2. Which Massachusetts regulation contains the State Building Code?
A. 527 CMR B. 780 CMR C. 248 CMR D. 310 CMR
Correct answer: B. 780 CMR
Rationale: The Massachusetts State Building Code is designated 780 CMR and incorporates
model codes and Massachusetts-specific amendments.
Massachusetts Government
3. What is the minimum passing score stated in the Massachusetts CSL candidate handbook?
A. 50% B. 60% C. 70% D. 80%
Correct answer: C. 70%
Rationale: The candidate handbook states that candidates must score at least 70% to pass an
examination.
Massachusetts Government
4. What is the primary purpose of a Construction Supervisor License?
, 2
A. To authorize electrical wiring without restrictions B. To establish qualification to supervise
construction work within the license's scope C. To replace all building permits D. To authorize
plumbing work automatically
Correct answer: B. To establish qualification to supervise construction work within the
license's scope
Rationale: A CSL qualifies an individual to supervise covered construction activities within
the applicable license category. It does not replace other trade licenses or permit
requirements.
Massachusetts Government
5. Which license category generally covers buildings of any use containing less than 35,000
cubic feet, as well as specified other structures?
A. Unrestricted CSL B. Electrical contractor license C. Plumbing license D. Demolition-only
permit
Correct answer: A. Unrestricted CSL
Rationale: Massachusetts describes the unrestricted license as covering specified
construction work, including buildings of any use below the stated enclosed-volume
threshold. The full scope and exceptions must be checked in the regulations.
Massachusetts Government
6. Which code edition is the basis of the current Massachusetts CSL examination program
that began in 2025?
A. Fifth Edition B. Seventh Edition C. Ninth Edition D. Tenth Edition
Correct answer: D. Tenth Edition
Rationale: Massachusetts transitioned CSL testing to the 10th Edition of the State Building
Code on January 1, 2025.
Massachusetts Government
7. What should a supervisor do if the approved construction drawings conflict with actual
site conditions?
, 3
A. Ignore the drawings B. Make any change without informing anyone C. Stop the affected
work and seek clarification through the appropriate design and approval process D. Cover
the discrepancy with finishes
Correct answer: C. Stop the affected work and seek clarification through the appropriate
design and approval process
Rationale: Unresolved discrepancies can affect structural integrity, code compliance, and
safety. Clarification should be obtained before proceeding with the affected work.
8. Who is responsible for determining whether a building permit is required for a proposed
project?
A. Only the material supplier B. The project team must comply with applicable permit rules
and confirm requirements with the local building official C. Only the homeowner's neighbor
D. The concrete delivery driver
Correct answer: B. The project team must comply with applicable permit rules and confirm
requirements with the local building official
Rationale: Permit requirements depend on the project and applicable regulations. The local
building department can clarify local requirements and the appropriate approval process.
9. What is the purpose of a building inspection?
A. To guarantee that a building will never fail B. To assess compliance with applicable code
requirements at the relevant construction stage C. To replace the contractor's quality-control
program D. To set the contractor's prices
Correct answer: B. To assess compliance with applicable code requirements at the relevant
construction stage
Rationale: Inspections help verify compliance with building requirements. They do not
eliminate the contractor's responsibility for workmanship, safety, and quality.
10. What should a supervisor do when an inspector identifies a code violation?
A. Conceal the violation B. Continue the affected work without review C. Understand the
violation, correct it as required, and arrange any necessary reinspection D. Remove the
inspection record
Correct answer: C. Understand the violation, correct it as required, and arrange any
necessary reinspection
Rationale: Correcting documented deficiencies and following the required approval process
helps establish compliance.
11. Why should construction drawings and specifications be available on site?