SSM TEST REVIEW QUESTIONS WITH
CORRECT ANSWERS
What is the definition of soil and foundation work? - CORRECT
| | | | | | | | | | |
ANSWER✔✔-Grading in soil or installing underpinning, Augering in soil | | | | | | | | |
or removing sheeting, Excavating and drilling in soil or rock
| | | | | | | | |
When contractors use light duty two-point adjustable suspended
| | | | | | | |
scaffolds in NYC, what - CORRECT ANSWER✔✔-¾'' grade #1 unspliced
| | | | | | | | | |
manila rope |
At what grade must power buggy brakes be capable of being fixed in
| | | | | | | | | | | | |
engagement to hold a full load stationary? - CORRECT ANSWER✔✔-25%
| | | | | | | | |
grade
|
The definition of _____________ is: a horizontal transverse scaffold
| | | | | | | | |
member (which may be supported by legs or runners) upon which the
| | | | | | | | | | | |
scaffold platform rests and joins scaffold uprights, posts, poles, and
| | | | | | | | | |
similar members - CORRECT ANSWER✔✔-Bearer (putlog)
| | | | |
The deck and the substantial enclosure of a sidewalk shed shall be
| | | | | | | | | | | |
extended parallel to the curb at least 20 feet beyond the building line
| | | | | | | | | | | | |
,when construction is_______ - CORRECT ANSWER✔✔-greater than 100
| | | | | | | |
feet
In structures undergoing demolition, how must the existing sprinkler
| | | | | | | | |
system be maintained - CORRECT ANSWER✔✔-Non-automatic and
| | | | | | |
Siamese hose connections shall be marked by a metal sign reading
| | | | | | | | | |
|"Sprinkler Siamese Connection" and by a red-light bulb at night
| | | | | | | | |
A ramp for a power buggy must be designed to support how many times
| | | | | | | | | | | | |
the maximum intended live load - CORRECT ANSWER✔✔-4
| | | | | | | |
The permanent floors of skeleton steel construction shall be installed as
| | | | | | | | | | |
soon as possible as steel installation progresses. In no case shall there
| | | | | | | | | | | |
be more than _________ or equivalent levels or __________, whichever
| | | | | | | | |
is less, between the erection floor and the uppermost permanent floor.
| | | | | | | | | | |
- CORRECT ANSWER✔✔-8 stories, 120 feet
| | | | | |
If an open excavation has been discontinued or interrupted for at least
| | | | | | | | | | | |
___ months, the lot shall be filled and graded to eliminate all steep
| | | | | | | | | | | | |
slopes, holes, obstructions, or similar sources of hazard. - CORRECT
| | | | | | | | | |
ANSWER✔✔-3
Excavated material and superimposed loads such as equipment, trucks,
| | | | | | | | |
etc., shall not be placed closer to the edge of the excavation than a
| | | | | | | | | | | | | |
distance equal __________ the depth of such excavation, unless the
| | | | | | | | | |
, excavation is in rock or unless the sides of the excavation have been
| | | | | | | | | | | | |
sloped or sheet piled (or sheeted) and shored to withstand the lateral
| | | | | | | | | | | |
force imposed by such superimposed loads. - CORRECT ANSWER✔✔-to
| | | | | | | | |
one and one-half times
| | |
The Commissioner shall inquire into the cause of any accident involving
| | | | | | | | | | |
equipment. When an accident involves any piece of equipment on the
| | | | | | | | | | |
site, no person shall do the following without the permission of the
| | | | | | | | | | | |
Commissioner: - CORRECT ANSWER✔✔-Use such equipment or remove | | | | | | |
the equipment or any part thereof from the area of the job site
| | | | | | | | | | | | |
According to 3314.8.2, the scaffold shall be enclosed with debris netting
| | | | | | | | | | |
consisting of a wire screen comprised of not less than _____ wire mesh,
| | | | | | | | | | | | |
or equivalent synthetic with a maximum _________ mesh. - CORRECT
| | | | | | | | | |
ANSWER✔✔-No. 18 steel, one-half inch | | | |
According to NYC DOB, how many years is the 32-Hour Rigging
| | | | | | | | | | |
Supervisor Training valid for and how many hours is the required
| | | | | | | | | | |
refresher course? - CORRECT ANSWER✔✔-4 years and 16 hours
| | | | | | | |
Specific to foundation operations that affect adjacent properties: The
| | | | | | | | |
owner of the property that may be affected shall be given ____ days
| | | | | | | | | | | | |
written notice of the intention to perform such operations. - CORRECT
| | | | | | | | | | |
ANSWER✔✔-10
CORRECT ANSWERS
What is the definition of soil and foundation work? - CORRECT
| | | | | | | | | | |
ANSWER✔✔-Grading in soil or installing underpinning, Augering in soil | | | | | | | | |
or removing sheeting, Excavating and drilling in soil or rock
| | | | | | | | |
When contractors use light duty two-point adjustable suspended
| | | | | | | |
scaffolds in NYC, what - CORRECT ANSWER✔✔-¾'' grade #1 unspliced
| | | | | | | | | |
manila rope |
At what grade must power buggy brakes be capable of being fixed in
| | | | | | | | | | | | |
engagement to hold a full load stationary? - CORRECT ANSWER✔✔-25%
| | | | | | | | |
grade
|
The definition of _____________ is: a horizontal transverse scaffold
| | | | | | | | |
member (which may be supported by legs or runners) upon which the
| | | | | | | | | | | |
scaffold platform rests and joins scaffold uprights, posts, poles, and
| | | | | | | | | |
similar members - CORRECT ANSWER✔✔-Bearer (putlog)
| | | | |
The deck and the substantial enclosure of a sidewalk shed shall be
| | | | | | | | | | | |
extended parallel to the curb at least 20 feet beyond the building line
| | | | | | | | | | | | |
,when construction is_______ - CORRECT ANSWER✔✔-greater than 100
| | | | | | | |
feet
In structures undergoing demolition, how must the existing sprinkler
| | | | | | | | |
system be maintained - CORRECT ANSWER✔✔-Non-automatic and
| | | | | | |
Siamese hose connections shall be marked by a metal sign reading
| | | | | | | | | |
|"Sprinkler Siamese Connection" and by a red-light bulb at night
| | | | | | | | |
A ramp for a power buggy must be designed to support how many times
| | | | | | | | | | | | |
the maximum intended live load - CORRECT ANSWER✔✔-4
| | | | | | | |
The permanent floors of skeleton steel construction shall be installed as
| | | | | | | | | | |
soon as possible as steel installation progresses. In no case shall there
| | | | | | | | | | | |
be more than _________ or equivalent levels or __________, whichever
| | | | | | | | |
is less, between the erection floor and the uppermost permanent floor.
| | | | | | | | | | |
- CORRECT ANSWER✔✔-8 stories, 120 feet
| | | | | |
If an open excavation has been discontinued or interrupted for at least
| | | | | | | | | | | |
___ months, the lot shall be filled and graded to eliminate all steep
| | | | | | | | | | | | |
slopes, holes, obstructions, or similar sources of hazard. - CORRECT
| | | | | | | | | |
ANSWER✔✔-3
Excavated material and superimposed loads such as equipment, trucks,
| | | | | | | | |
etc., shall not be placed closer to the edge of the excavation than a
| | | | | | | | | | | | | |
distance equal __________ the depth of such excavation, unless the
| | | | | | | | | |
, excavation is in rock or unless the sides of the excavation have been
| | | | | | | | | | | | |
sloped or sheet piled (or sheeted) and shored to withstand the lateral
| | | | | | | | | | | |
force imposed by such superimposed loads. - CORRECT ANSWER✔✔-to
| | | | | | | | |
one and one-half times
| | |
The Commissioner shall inquire into the cause of any accident involving
| | | | | | | | | | |
equipment. When an accident involves any piece of equipment on the
| | | | | | | | | | |
site, no person shall do the following without the permission of the
| | | | | | | | | | | |
Commissioner: - CORRECT ANSWER✔✔-Use such equipment or remove | | | | | | |
the equipment or any part thereof from the area of the job site
| | | | | | | | | | | | |
According to 3314.8.2, the scaffold shall be enclosed with debris netting
| | | | | | | | | | |
consisting of a wire screen comprised of not less than _____ wire mesh,
| | | | | | | | | | | | |
or equivalent synthetic with a maximum _________ mesh. - CORRECT
| | | | | | | | | |
ANSWER✔✔-No. 18 steel, one-half inch | | | |
According to NYC DOB, how many years is the 32-Hour Rigging
| | | | | | | | | | |
Supervisor Training valid for and how many hours is the required
| | | | | | | | | | |
refresher course? - CORRECT ANSWER✔✔-4 years and 16 hours
| | | | | | | |
Specific to foundation operations that affect adjacent properties: The
| | | | | | | | |
owner of the property that may be affected shall be given ____ days
| | | | | | | | | | | | |
written notice of the intention to perform such operations. - CORRECT
| | | | | | | | | | |
ANSWER✔✔-10