Question 1.
The type and extent of each special inspection shall be located in
ANSWER
The statement of special inspection
Question 2.
Who has the legal authority to enforce the special inspection provisions of the building code
ANSWER
Building official
Question 3.
Who can hire an approved inspection agency
ANSWER
Owners agent
Question 4.
Who can perform a structural observation
ANSWER
Registered design professional
Question 5.
Who is required to receive the final report
ANSWER
Building department
Question 6.
All of the following should be performed by the special inspector on the job site except
ANSWER
Stop work when non-conforming items are observed
1
, Question 7.
Who is responsible for providing access to the approved plans
ANSWER
General contractor
Question 8.
Who shall the special inspector demonstrate competence to
ANSWER
Building official
Question 9.
Who can issue a stop work order
ANSWER
Building official
Question 10.
What type of inspection is required for post installed adhesive anchors (epoxy) placed in a
horizontal position into an existing 4000 PSI concrete wall
ANSWER
Continuous special inspection
Question 11.
Which of the following does not need to be on a daily report containing non-conforming items
ANSWER
A proposed solution from the special inspector
Question 12.
Discrepancies should be brought to the Immediate attention of the what extent of special
inspection
ANSWER
Contractor
Question 13.
Who must a special inspector notify of their presence on a job site
ANSWER
Contractor
2
WITH VERIFIED ANSWERS
Question 1.
The type and extent of each special inspection shall be located in
ANSWER
The statement of special inspection
Question 2.
Who has the legal authority to enforce the special inspection provisions of the building code
ANSWER
Building official
Question 3.
Who can hire an approved inspection agency
ANSWER
Owners agent
Question 4.
Who can perform a structural observation
ANSWER
Registered design professional
Question 5.
Who is required to receive the final report
ANSWER
Building department
Question 6.
All of the following should be performed by the special inspector on the job site except
ANSWER
Stop work when non-conforming items are observed
1
, Question 7.
Who is responsible for providing access to the approved plans
ANSWER
General contractor
Question 8.
Who shall the special inspector demonstrate competence to
ANSWER
Building official
Question 9.
Who can issue a stop work order
ANSWER
Building official
Question 10.
What type of inspection is required for post installed adhesive anchors (epoxy) placed in a
horizontal position into an existing 4000 PSI concrete wall
ANSWER
Continuous special inspection
Question 11.
Which of the following does not need to be on a daily report containing non-conforming items
ANSWER
A proposed solution from the special inspector
Question 12.
Discrepancies should be brought to the Immediate attention of the what extent of special
inspection
ANSWER
Contractor
Question 13.
Who must a special inspector notify of their presence on a job site
ANSWER
Contractor
2