SOS NERC PREP - RELIABILITY EXAM UPDATED
ACTUAL QUESTIONS AND CORRECT ANSWERS
Question:
1. The Reliability Coordinator just informed you of a slow time error correction which will begin at
the top of the next hour. Your EMS system will not let you change your scheduled frequency. Your
Frequency Bias Setting is -100 MW/.1Hz. What action should you take?
A) Increase Net Interchange Schedule by 20 MWs.
B) Inform the Reliability Coordinator that you cannot participate in the time error correction.
C) Decrease Net Interchange Schedule by 20 MWs.
D) Increase Net Interchange Schedule by 10 MWs.
Answer:
A) Increase Net Interchange Schedule by 20 MWs.

Question:
2. A Balancing Authority has a sudden loss of a large block of load in its area. This loss will be seen
instantaneously in the change of which of the following values?
1. Actual Net Interchange
2. Scheduled Frequency
3. Scheduled Net Interchange
4. Area Control Error
A) 4 only
B) 1 & 3
C) 1 & 4
D) 3 & 4
Answer:
C) 1 & 4

Question:
3. Metered Data included in the calculation of ACE are: dynamic schedules, pseudo ties, actual
frequency, and all __________.
A) Tie lines readings
B) Generators output
C) Scheduled frequency indications
D) Transformer load
Answer:
A) Tie lines readings

Question:
4. Balancing Authority A is currently reading a system frequency of 60.00 Hz. Its Net Actual
Interchange is +100 MW and its Net Scheduled Interchange is +200 MW. If Balancing Authority A's
frequency bias setting is 100 MW/0.1 Hz, what is ACE?
A) -100
B) 0
C) 10
D) 100
Answer:
A) -100

,Question:
5. A Balancing Authority has a Net Interchange Schedule of
-250 MWs from 1200 to 1600 on a summer day. The Net Interchange Actual for those same hours
respectively were -230 MW, -275 MW, -250 MW and -270 MW. What was the Balancing Authority's
Inadvertent Interchange for the 4-hour period?
A) 6 MWs out
B) 25 MWs in
C) 25 MWs out
D) 6 MWs in
Answer:
B) 25 MWs in

Question:
6. For the ACE equation to work properly, dynamic schedules, pseudo ties, frequency, and all
________________ must be metered.
A) Generation
B) Communications
C) Transformers
D) Tie lines
Answer:
D) Tie lines

Question:
7. If the frequency bias setting is set to a less negative value than the frequency response of a
Balancing Authority and a frequency increase is caused by a sudden loss of load in an external
balancing area, what will be the result?
A) The ACE will be zero and will take no AGC action
B) The ACE will be a negative value and AGC will increase generation
C) The ACE will be a positive value and AGC will lower generation
D)This will not affect the ACE
Answer:
B) The ACE will be a negative value and AGC will increase generation

Question:
8. If the frequency bias setting is less negative than the frequency response of a Balancing Authority
and a frequency decline is caused by a sudden loss of generation in an external balancing area, what
will be the result?
A) The ACE will be a negative value and AGC will increase generation.
B) This will not affect the ACE.
C) The ACE will be a positive value and AGC will lower generation.
D) The ACE will be zero and will take no AGC action.
Answer:
C) The ACE will be a positive value and AGC will lower generation.

, Question:
9. It is the responsibility of which entity/entities to develop, maintain, and implement load shedding
plans?
A) Transmission Operators and Balancing Authorities
B) Reliability Coordinator
C) Load Serving Entities
D) Balancing Authority
Answer:
A) Transmission Operators and Balancing Authorities

Question:
10. A Transmission line is loaded 25% above its SOL. A parallel line is out for routine maintenance
and can be placed in service in 10 minutes. What is the first step the Operator should take to reduce the
line loading?
A)Shed load at the downstream bus.
B) Open the line.
C) Re-Dispatch Generation.
D) Initiate the restoration of the parallel line.
Answer:
D) Initiate the restoration of the parallel line.

Question:
11. As a Transmission Operator, you realize that the voltage level is starting to decline in the North
West part of the system. Which of the following devices should you, as a Transmission Operator, be
able to operate, and/or have another entity operate to raise the voltage level back to normal in the
North West part of the system?
A) Transformer Underload Tap Changers
B) Shunt Capacitor Banks
C) Generator Reactive Output
D) All answers are correct
Answer:
D) All answers are correct

Question:
12. Voltage reduction for load relief should be made on the __________.
A) Distribution system
B) Entire Interconnection simultaneously
C) Tie-lines with other Balancing Authority Areas
D) Transmission System
Answer:
A) Distribution system

Question:
13. Under Frequency Load Shedding (UFLS) is to stabilize the imbalance between generation and
load that has been created by a system disturbance. This is accomplished by ____________.
A) Tripping generation first
B) Voltage reduction on the distribution system.
C) Shedding all load to arrest frequency
D) Shedding load prior to generation tripping

Document information

Uploaded on
October 7, 2026
Number of pages
24
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$13.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
STANFORDGRADESS
4.0
(240)
Sold
1646
Followers
108
Items
119944
Last sold
6 hours ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions