OCSM exam 2 | UPDATED Questions with 100% Verified
Answers
Q1: Work Measurement Techniques
A: Methods used to determine time required to perform a task


Q2: Standard Elemental Times
A: Uses historical time data for repetitive tasks


Q3: Predetermined Time Standards (PTS)
A: Uses motion/time systems without direct observation


Q4: Work Sampling
A: Random observations used to estimate time spent on activities


Q5: Stopwatch Time Study
A: Direct timing of a task using a stopwatch


Q6: Work Sampling Formula
A: n = (z/e)² × p■ (1 − p■ )


Q7: Work Sampling Advantage
A: Low cost, minimal disruption


Q8: Work Sampling Disadvantage
A: Less precise, requires many observations


Q9: Observed Time (OT)
A: Average time of observations (sum of times ÷ number of observations)


Q10: Normal Time (NT)
A: OT × Performance Rating


Q11: Standard Time (ST)
A: NT × Allowance Factor


Q12: Performance Rating (PR)
A: Adjustment factor based on worker speed vs standard

, Q13: Allowance Factor (AF)
A: Accounts for breaks, fatigue, delays


Q14: AF (job)
A: 1 + A


Q15: AF (day)
A: 1 / (1 − A)


Q16: Work Sampling vs Stopwatch Study
A: Sampling = cheaper, less precise; Stopwatch = more accurate, more costly


Q17: Forward Scheduling
A: Start jobs as soon as possible


Q18: Backward Scheduling
A: Start from due date and work backward


Q19: Infinite Loading
A: Assigns work without considering capacity


Q20: Finite Loading
A: Assigns work based on actual capacity limits


Q21: FCFS Rule
A: Jobs processed in order they arrive


Q22: SPT Rule
A: Shortest processing time first


Q23: EDD Rule
A: Earliest due date first


Q24: Critical Ratio (CR)
A: Time remaining ÷ processing time


Q25: CR < 1
A: Job is behind schedule

Document information

Uploaded on
October 7, 2026
Number of pages
8
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$13.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
ExamsCollection
3.9
(45)
Sold
259
Followers
9
Items
40196
Last sold
19 hours ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions