What are the inputs of controlling a schedule?
Give this one a try later!
Project Management Plan
Project Schedule
Work Performance Data
Project Calendars
Schedule Data
Organizational Process Assets
What are the five steps to defining the project?
Give this one a try later!
Step 1: Defining the Project Scope
Step 2: Establishing Project Priorities
Step 3: Creating the Work Breakdown Structure
, Step 4: Integrating the WBS with the Organization
Step 5: Coding the WBS for the Information System
What are the tools & techniques for validating scope (monitoring & controlling)?
Give this one a try later!
Inspection
Group Decision Making Techniques
What are the tools & techniques for determining a budget?
Give this one a try later!
Cost Aggregation
Reserve Analysis
Expert Judgment
Historical Relationships
Funding Limit Reconciliation
What are the inputs for controlling cost?
Give this one a try later!
Cost Management Plan
Project Funding Requirements
Work Performance Data
Organizational Process Assets
,What are the tools & techniques for developing a project character?
Give this one a try later!
Expert judgement
What are the different knowledge areas?
Give this one a try later!
Integration, scope, time, cost, quality, human resources, communications,
risk, procurement, stakeholders
What is the checklist model for selection models?
Give this one a try later!
Uses a list of questions to review potential projects and to determine their
acceptance or rejection.
Fails to answer the relative importance or value of a potential project and
doesn't allow for comparison with other potential projects.
What do internal projects do?
Give this one a try later!
, Internal projects help companies implement internal initiatives that serve
their strategy and don't directly make money
What are the outputs for estimate activity durations?
Give this one a try later!
Activity Duration Estimates
Project Documents Updates
What is the preferred approach to estimating a project?
Give this one a try later!
-Make rough top-down estimates
-Develop the WBS
-Make bottom-up estimates
-Develop schedules and budgets
-Reconcile
What are the outputs for creating a WBS (planning)?
Give this one a try later!
Scope Baseline
Project Documents Updates
Give this one a try later!
Project Management Plan
Project Schedule
Work Performance Data
Project Calendars
Schedule Data
Organizational Process Assets
What are the five steps to defining the project?
Give this one a try later!
Step 1: Defining the Project Scope
Step 2: Establishing Project Priorities
Step 3: Creating the Work Breakdown Structure
, Step 4: Integrating the WBS with the Organization
Step 5: Coding the WBS for the Information System
What are the tools & techniques for validating scope (monitoring & controlling)?
Give this one a try later!
Inspection
Group Decision Making Techniques
What are the tools & techniques for determining a budget?
Give this one a try later!
Cost Aggregation
Reserve Analysis
Expert Judgment
Historical Relationships
Funding Limit Reconciliation
What are the inputs for controlling cost?
Give this one a try later!
Cost Management Plan
Project Funding Requirements
Work Performance Data
Organizational Process Assets
,What are the tools & techniques for developing a project character?
Give this one a try later!
Expert judgement
What are the different knowledge areas?
Give this one a try later!
Integration, scope, time, cost, quality, human resources, communications,
risk, procurement, stakeholders
What is the checklist model for selection models?
Give this one a try later!
Uses a list of questions to review potential projects and to determine their
acceptance or rejection.
Fails to answer the relative importance or value of a potential project and
doesn't allow for comparison with other potential projects.
What do internal projects do?
Give this one a try later!
, Internal projects help companies implement internal initiatives that serve
their strategy and don't directly make money
What are the outputs for estimate activity durations?
Give this one a try later!
Activity Duration Estimates
Project Documents Updates
What is the preferred approach to estimating a project?
Give this one a try later!
-Make rough top-down estimates
-Develop the WBS
-Make bottom-up estimates
-Develop schedules and budgets
-Reconcile
What are the outputs for creating a WBS (planning)?
Give this one a try later!
Scope Baseline
Project Documents Updates