2026/2027: 80 Solved Questions on Critical
Path, Float, PERT, Crashing, EVM & CCPM
— Complete Test Bank with Explanations,
Formula Sheet and Marking Rubric for
University Students
Description:
Ace your 2026/2027 project management midterm with this exam-ready test bank covering
critical path method, float analysis, PERT estimation, crashing, fast tracking, resource
leveling, schedule baseline, EVM, SPI, SV, and Critical Chain Project Management.
Includes 80 solved multiple-choice questions with detailed explanations, five essay prompts, a
full essay marking rubric, formula sheet, topic coverage map, and marking scheme. Perfect for
university exams, PMP prep, and self-study. Aligned with current PMBOK standards and
emerging scheduling practices.
Download now and walk into your exam confident, prepared, and ready to score top marks — your
success starts here.
, Project Management Scheduling Exam 2026/2027: 80 Practice
Questions + Answers
Section A: Fundamentals of Project Schedule Management
(Questions 1–25)
1. Which of the following statements most accurately describes the role of the critical path
in project management?
A. The critical path provides a definitive guarantee of the project's final completion date.
B. A project network can only ever contain a single critical path.
C. The critical path identifies the sequence of activities that determines the shortest possible
project duration.
D. A project can never exhibit negative float on any of its activities.
Answer: C
Explanation: The critical path is the longest sequence of dependent activities in a project
network diagram. It determines the shortest possible time in which the entire project can be
completed. It does not guarantee the completion date (A), as risks and changes can occur. A
project can have multiple critical paths (B). Negative float is possible when a project is behind
schedule (D).
2. During a project status meeting, a team member proposes a technical change to her
activity that will increase its duration. According to best practices in integrated change
control, what is the project manager's first step?
A. Immediately approve the change to maintain team morale.
B. Assess the impact of the change on the project's critical path.
C. Reject the change to protect the project baseline.
D. Escalate the request to the project sponsor for a final decision.
Answer: B
,Explanation: The first step in managing any potential change is to understand its impact. The
project manager must analyze how the added time will affect the overall project schedule. If the
activity is on the critical path, the change will directly delay the project. If it has float, the delay
may be absorbed without impacting the final deadline.
3. Senior management has expressed difficulty in quickly assessing the overall health and
progress of numerous ongoing projects. Which type of report would be most effective in
providing this high-level, summary information?
A. Detailed Gantt charts for each project.
B. Milestone reports.
C. Daily stand-up meeting minutes.
D. Individual activity cost reports.
Answer: B
Explanation: Milestone reports are designed to provide a high-level overview of project
progress by focusing on the achievement of key events or milestones. This format is ideal for
senior executives who need a concise summary rather than detailed operational data.
4. A project manager for a small construction company has a project that was budgeted for
US $130,000 over a six-week period. According to her schedule, the project should have
cost US $60,000 to date. However, it has cost US $90,000 to date. The project is also behind
schedule because the original estimates were not accurate. Who has the PRIMARY
responsibility to solve this problem?
A. The project sponsor.
B. The functional manager.
C. The project manager.
D. The senior management.
Answer: C
Explanation: The project manager is the individual ultimately responsible for the day-to-day
management and success of the project. This includes managing the budget, schedule, and
, resources. When a project encounters issues such as cost overruns and schedule delays, it is the
project manager's primary responsibility to identify the root causes and develop corrective action
plans.
5. A project manager is reanalyzing the project to predict its duration by focusing on the
sequence of activities with the least amount of scheduling flexibility. Which scheduling
technique is she applying?
A. Critical Chain Method
B. Resource Leveling
C. Critical Path Method
D. Monte Carlo Simulation
Answer: C
Explanation: The Critical Path Method (CPM) is a scheduling technique that identifies the
longest path of dependent activities through a project network. This path, known as the critical
path, has zero float (or the least scheduling flexibility). By analyzing this sequence, the project
manager can predict the minimum project duration.
6. Which of the following best defines "float" in the context of project schedule
management?
A. The total duration of all non-critical activities.
B. The amount of time an activity can be delayed without affecting the project's critical path.
C. The amount of time an activity can be delayed without delaying the early start of its
successor.
D. The difference between the optimistic and pessimistic estimates.
Answer: B
Explanation: Float, also known as slack, is the amount of time an activity can be delayed
without causing a delay to the project's completion date or the start of a subsequent activity.
Total float refers to the delay without affecting the project end date, while free float refers to the
delay without affecting the early start of the successor activity.