A 15 kV vacuum circuit breaker undergoes timing tests. The closing time is 85
ms, opening time 45 ms, and pole discrepancy 3 ms. Per ANSI/NETA
ETT-2026, which parameter exceeds the maximum allowable limit for this
breaker type?
A. Closing time only
B. Opening time only
C. Pole discrepancy only
D. Both closing time and pole discrepancy
Correct Answer: A - Closing time only
RATIONALE
NETA ETT-2026 Table 100.7 specifies maximum closing time of 80
ms for vacuum breakers; 85 ms exceeds this. Opening time (45 ms)
and pole discrepancy (3 ms) are within limits (50 ms and 5 ms,
respectively). Thus, only closing time is non-compliant.
Question 2
During insulation resistance testing of a 5 kV motor winding, readings at 1
minute and 10 minutes are 500 M and 800 M, respectively. The winding
temperature is 40°C. What is the polarization index (PI) and its interpretation
per NETA ETT-2026?
A. PI = 1.6, acceptable
B. PI = 1.6, questionable; investigate
C. PI = 0.625, unacceptable
D. PI = 2.0, excellent
Correct Answer: B - PI = 1.6, questionable; investigate
Page 2
, RATIONALE
PI = 10-min IR / 1-min IR = 800/500 = 1.6. NETA ETT-2026
considers PI 2.0 as good, 1.5-2.0 as questionable requiring further
investigation, and <1.5 as poor. A PI of 1.6 indicates marginal
insulation condition, necessitating additional tests like step-voltage or
dissipation factor.
Question 3
A transformer turns ratio test on a 13.8 kV-480 V, 1 MVA, delta-wye
transformer yields a measured ratio of 28.5:1. The nameplate ratio is 28.75:1.
What is the percent error, and does it comply with NETA ETT-2026?
A. 0.87% error, complies
B. 0.87% error, does not comply
C. 1.0% error, complies
D. 1.0% error, does not comply
Correct Answer: A - 0.87% error, complies
RATIONALE
Percent error = |28.5 - 28.75| / 28.75 × 100 0.87%. NETA ETT-2026
allows a maximum ratio error of ±0.5% for transformers. Since 0.87%
exceeds this, it does not comply, but the question asks for error and
compliance; 0.87% is correct, but compliance is 'does not
comply'-however, option A says complies, which is wrong. Wait: The
correct answer should be B. Let me recalc: 28.75-28.5=0.25;
0.25/28.75=0.008695=0.87%. NETA Table 100.3 allows ±0.5% for
turns ratio. So 0.87% > 0.5%, so does not comply. Thus correct is B. I
need to correct my answer. The initial correct was A, but it's B. Let me
fix: The correct option is B. Explanation: Error is 0.87%, which
exceeds the ±0.5% tolerance, so it does not comply.
Page 3
, Question 4
A ground grid resistance test using the fall-of-potential method yields 3.5 . The
system is a 13.8 kV substation with a fault current of 10 kA and a clearing time
of 0.5 s. Per IEEE 80 and NETA ETT-2026, what is the maximum allowable
grid resistance to ensure step and touch voltages are safe?
A. 1.0
B. 2.5
C. 5.0
D. 10.0
Correct Answer: C - 5.0
RATIONALE
IEEE 80 does not specify a fixed maximum grid resistance; instead, it
requires that step and touch voltages be within tolerable limits.
However, NETA ETT-2026 Table 100.18 suggests a target of 5 for
substation grounds, but the actual criterion is safety. A 3.5 reading is
generally acceptable if step/touch voltages are safe. Among options,
5.0 is the typical maximum guideline.
Question 5
A protective relay coordination study shows that the upstream feeder breaker's
time-delay setting is 0.3 s, while the downstream breaker's instantaneous
setting is 0.1 s. What is the coordination time interval (CTI), and does it meet
NETA ETT-2026 recommendations?
A. 0.2 s, meets
B. 0.2 s, does not meet
C. 0.4 s, meets
D. 0.4 s, does not meet
Correct Answer: A - 0.2 s, meets