AVIXA CTS TEST BANK QUESTIONS WITH
VERIFIED ANSWERS FULL REVIEW
●● [Conducting Site Rough-In/ First-Fix/Mount Substructure]
When mounting a 34kg (75lb) projector with a 7kg (15lb) mount, the
substructure should be able to support a minimum weight of:
A. 82kg (1801b)
B. 41kg (90lb)
C. 204kg (450lb)
D. 122kg (270lb)
Answer: C. 204kg (450lb)
●● 3. [Installing Audiovisual Systems/Prepare Audiovisual Rack]
Where should you place the wireless microphone receiver antenna in a
rack assembly?
A. Line of sight to the transmitter
B. Inside the transmitter room
C. In the front of the rack
D. At the rear of the rack
Answer: C. In the front of the rack
,●● 4. [Performing Systems Closeout/Provide Training on Equipment
Operation]
When training a customer on the operation of a touch-panel interface, an
example that the GUI is a good design that meets the customer's needs
is:
A. The customer can easily use the touch panel with little explanation
B. The customer requires intensive training on how to use the touch
panel
C. The customer thinks the panel looks cool
D. The customer wants only a few changes
Answer: A. The customer can easily use the touch panel with little
explanation
●● 1. Before developing a project plan, it is important to:
A. Make sure the client has made a deposit payment
B. Have a clear understanding of the scope of work
C. Order the AV equipment needed
D. List all the teams that will work on the project
Answer: B. Have a clear understanding of the scope of work
,●● 2. A scope statement should include:
A. Only the items within the project scope
B. Only the items within the deliverable scope
C. All the tasks that have to be performed
D. Both in-scope and out-of-scope items
Answer: D. Both in-scope and out-of-scope items
●● 3. The key elements of a project should be driven by:
A. The cost of materials
B. The overall budget
C. The client's need
D. The deadline for completion
Answer: C. The client's need
●● 4. What is a dependency within a project task schedule?
A. A task that cannot begin before another task has been completed
B. A task that must be completed by a specific date
C. A task that will be required if specific conditions occur at the project
site
, D. An optional task that the client can determine is needed once the
project is underway
Answer: A. A task that cannot begin before another task has been
completed
●● 5. Project budget refers to which of the following?
A. The amount of labor and materials the project manager has allocated
to complete the project
B. The total amount that the client has paid the AV company for the
project
C. The amount needed for purchasing the materials and supplies
D. The actual cost of labor and materials used to complete the project
Answer: A. The amount of labor and materials the project manager has
allocated to complete the project
●● 6. A primary reason for attending construction meetings is to:
A. Develop a relationship with the other people on the job
B. Identify changes to the original design that will affect the AV
installation
C. Find out the project's completion date
D. Submit invoices and other budget documentation
VERIFIED ANSWERS FULL REVIEW
●● [Conducting Site Rough-In/ First-Fix/Mount Substructure]
When mounting a 34kg (75lb) projector with a 7kg (15lb) mount, the
substructure should be able to support a minimum weight of:
A. 82kg (1801b)
B. 41kg (90lb)
C. 204kg (450lb)
D. 122kg (270lb)
Answer: C. 204kg (450lb)
●● 3. [Installing Audiovisual Systems/Prepare Audiovisual Rack]
Where should you place the wireless microphone receiver antenna in a
rack assembly?
A. Line of sight to the transmitter
B. Inside the transmitter room
C. In the front of the rack
D. At the rear of the rack
Answer: C. In the front of the rack
,●● 4. [Performing Systems Closeout/Provide Training on Equipment
Operation]
When training a customer on the operation of a touch-panel interface, an
example that the GUI is a good design that meets the customer's needs
is:
A. The customer can easily use the touch panel with little explanation
B. The customer requires intensive training on how to use the touch
panel
C. The customer thinks the panel looks cool
D. The customer wants only a few changes
Answer: A. The customer can easily use the touch panel with little
explanation
●● 1. Before developing a project plan, it is important to:
A. Make sure the client has made a deposit payment
B. Have a clear understanding of the scope of work
C. Order the AV equipment needed
D. List all the teams that will work on the project
Answer: B. Have a clear understanding of the scope of work
,●● 2. A scope statement should include:
A. Only the items within the project scope
B. Only the items within the deliverable scope
C. All the tasks that have to be performed
D. Both in-scope and out-of-scope items
Answer: D. Both in-scope and out-of-scope items
●● 3. The key elements of a project should be driven by:
A. The cost of materials
B. The overall budget
C. The client's need
D. The deadline for completion
Answer: C. The client's need
●● 4. What is a dependency within a project task schedule?
A. A task that cannot begin before another task has been completed
B. A task that must be completed by a specific date
C. A task that will be required if specific conditions occur at the project
site
, D. An optional task that the client can determine is needed once the
project is underway
Answer: A. A task that cannot begin before another task has been
completed
●● 5. Project budget refers to which of the following?
A. The amount of labor and materials the project manager has allocated
to complete the project
B. The total amount that the client has paid the AV company for the
project
C. The amount needed for purchasing the materials and supplies
D. The actual cost of labor and materials used to complete the project
Answer: A. The amount of labor and materials the project manager has
allocated to complete the project
●● 6. A primary reason for attending construction meetings is to:
A. Develop a relationship with the other people on the job
B. Identify changes to the original design that will affect the AV
installation
C. Find out the project's completion date
D. Submit invoices and other budget documentation