NYC DCAS Construction Project Manager Exam
Practice Questions And Correct Answers (Verified
Answers) Plus Rationale 2026 Q&A
NYC DCAS Construction Project Manager Exam – Practice Q&A Exam 3042 /
5058 |Verified Answers with Rationales
EXAM OVERVIEW
The NYC Department of Citywide Administrative Services (DCAS) Construction
Project Manager Exam (Nos. 3042 & 5058) assesses candidates for project
management roles within New York City agencies . The exam covers key areas
including project planning, scheduling, budgeting, contract administration, safety
management, and NYC-specific regulations.
Eligibility Requirements:
- High school diploma + 5 years of construction project management/inspection
experience (projects ≥ $300,000)
- OR 1 year experience + bachelor's degree in engineering, architecture,
construction, or related field
- OR 1 year experience + valid PE, RA, or RLA license
- Valid NYS driver license required
1
,SECTION 1: CONSTRUCTION DOCUMENTS & CONTRACTS
Question 1
Which document defines the project scope, schedule, and budget in NYC
municipal construction?
A) Blueprints
B) Permit application
C) Contract specifications
D) Work order
Correct Answer: C
Rationale: Contract specifications clearly outline project expectations, including
scope, timeline, and cost. They are the legally binding documents that define what
is to be built and how . Blueprints show design but not budget/schedule details.
Question 2
What is the primary purpose of a construction contract bond?
2
,A) To fund project materials
B) To guarantee the contractor will fulfill contractual obligations
C) To pay workers' salaries
D) To insure equipment
Correct Answer: B
Rationale: Contract bonds protect the owner by ensuring the contractor completes
the work according to the contract terms. If the contractor defaults, the surety
compensates the owner .
Question 3
Which type of contract places most of the financial risk on the contractor?
A) Time and materials
B) Cost-plus contract
C) Lump-sum (fixed-price) contract
D) Unit-price contract
3
, Correct Answer: C
Rationale: In lump-sum contracts, the contractor agrees to a fixed price, so any cost
overruns are their responsibility. This transfers maximum financial risk to the
contractor .
Question 4
What is the purpose of a change order?
A) To hire new subcontractors
B) To formally modify contract terms, including scope, schedule, or cost
C) To approve invoices
D) To assign new tasks to the team
Correct Answer: B
Rationale: Change orders officially adjust the original contract to accommodate
changes in work scope, schedule, or cost, ensuring both parties agree to the
modifications . They are essential for managing project changes.
4
Practice Questions And Correct Answers (Verified
Answers) Plus Rationale 2026 Q&A
NYC DCAS Construction Project Manager Exam – Practice Q&A Exam 3042 /
5058 |Verified Answers with Rationales
EXAM OVERVIEW
The NYC Department of Citywide Administrative Services (DCAS) Construction
Project Manager Exam (Nos. 3042 & 5058) assesses candidates for project
management roles within New York City agencies . The exam covers key areas
including project planning, scheduling, budgeting, contract administration, safety
management, and NYC-specific regulations.
Eligibility Requirements:
- High school diploma + 5 years of construction project management/inspection
experience (projects ≥ $300,000)
- OR 1 year experience + bachelor's degree in engineering, architecture,
construction, or related field
- OR 1 year experience + valid PE, RA, or RLA license
- Valid NYS driver license required
1
,SECTION 1: CONSTRUCTION DOCUMENTS & CONTRACTS
Question 1
Which document defines the project scope, schedule, and budget in NYC
municipal construction?
A) Blueprints
B) Permit application
C) Contract specifications
D) Work order
Correct Answer: C
Rationale: Contract specifications clearly outline project expectations, including
scope, timeline, and cost. They are the legally binding documents that define what
is to be built and how . Blueprints show design but not budget/schedule details.
Question 2
What is the primary purpose of a construction contract bond?
2
,A) To fund project materials
B) To guarantee the contractor will fulfill contractual obligations
C) To pay workers' salaries
D) To insure equipment
Correct Answer: B
Rationale: Contract bonds protect the owner by ensuring the contractor completes
the work according to the contract terms. If the contractor defaults, the surety
compensates the owner .
Question 3
Which type of contract places most of the financial risk on the contractor?
A) Time and materials
B) Cost-plus contract
C) Lump-sum (fixed-price) contract
D) Unit-price contract
3
, Correct Answer: C
Rationale: In lump-sum contracts, the contractor agrees to a fixed price, so any cost
overruns are their responsibility. This transfers maximum financial risk to the
contractor .
Question 4
What is the purpose of a change order?
A) To hire new subcontractors
B) To formally modify contract terms, including scope, schedule, or cost
C) To approve invoices
D) To assign new tasks to the team
Correct Answer: B
Rationale: Change orders officially adjust the original contract to accommodate
changes in work scope, schedule, or cost, ensuring both parties agree to the
modifications . They are essential for managing project changes.
4