●● CQC
Answer: contractor quality control
●● Superpave
Answer: Asphalt mix design system since 1998
●● QCP
Answer: Quality control plan
●● QCM
Answer: Quality control Manual
●● QC
Answer: Quality Control (Contracting Testing and Inspection)
●● VT
Answer: Verification Testing (FDOT or CEI Verification)
●● CEI
,Answer: Construction Engineering and Inspection
●● RT
Answer: Resolution Testing (FDOT)
●● IV
Answer: Independent Verification Testing
●● IA
Answer: Independent Assurance Testing
●● The decision-making authority on a job needs to be given to who?
Answer: Needs to be given to the level closet to the work as specified in
the specifications. It ensure a quick handle on situations and issues.
●● The governing order of project documents from high (1) to low (7)
starts with the highest being
Answer: Special Provisions
●● The governing order of project documents from high to low (2)
Answer: Technical Special Provisions
●● The governing order of project documents from high to low (3)
, Answer: Plans
●● The governing order of project documents from high to low (4)
Answer: Road design, structures, and traffic operations standards
●● The governing order of project documents from high to low (5)
Answer: Developmental Specifications
●● The governing order of project documents from high to low (6)
Answer: Supplemental Specifications
●● The governing order of project documents from high to low (7)
Answer: Standard Specifications
●● What are the key components in a pre-paving conferences?
Answer: Key Personnel (Paving superintendent)
Contractor Input
Agency Input
QC Plan Review
Discuss more specific key topics or issues
Meeting Minutes
Action items (what to do in situations, who to call)
AND ANSWERS VERIFIED REVIEW
●● CQC
Answer: contractor quality control
●● Superpave
Answer: Asphalt mix design system since 1998
●● QCP
Answer: Quality control plan
●● QCM
Answer: Quality control Manual
●● QC
Answer: Quality Control (Contracting Testing and Inspection)
●● VT
Answer: Verification Testing (FDOT or CEI Verification)
●● CEI
,Answer: Construction Engineering and Inspection
●● RT
Answer: Resolution Testing (FDOT)
●● IV
Answer: Independent Verification Testing
●● IA
Answer: Independent Assurance Testing
●● The decision-making authority on a job needs to be given to who?
Answer: Needs to be given to the level closet to the work as specified in
the specifications. It ensure a quick handle on situations and issues.
●● The governing order of project documents from high (1) to low (7)
starts with the highest being
Answer: Special Provisions
●● The governing order of project documents from high to low (2)
Answer: Technical Special Provisions
●● The governing order of project documents from high to low (3)
, Answer: Plans
●● The governing order of project documents from high to low (4)
Answer: Road design, structures, and traffic operations standards
●● The governing order of project documents from high to low (5)
Answer: Developmental Specifications
●● The governing order of project documents from high to low (6)
Answer: Supplemental Specifications
●● The governing order of project documents from high to low (7)
Answer: Standard Specifications
●● What are the key components in a pre-paving conferences?
Answer: Key Personnel (Paving superintendent)
Contractor Input
Agency Input
QC Plan Review
Discuss more specific key topics or issues
Meeting Minutes
Action items (what to do in situations, who to call)