PMP PRACTICE EXAM PRACTICE QUESTIONS AND CORRECT ANSWERS (VERIFIED ANSWERS) PLUS

Content preview

s Batch 1

PMP PRACTICE EXAM PRACTICE QUESTIONS AND CORRECT ANSWERS
(VERIFIED ANSWERS) PLUS RATIONALE Q&A



PMP Practice Exam – Batch 1 (Questions 1–50)

Directions: Each question is followed by four answer choices. Select the
best answer based on PMI-aligned thinking.



Questions 1–10: People Domain – Team Leadership & Development

1. A project manager is leading a distributed team across three time
zones. Two team members have conflicting work styles that are causing
delays. What should the project manager do FIRST?



A) Escalate the conflict to the functional managers

B) Reassign one team member to a different project

C) Facilitate a direct conversation between the two team members to
resolve the conflict

D) Ignore the conflict and allow the team to self-organize



Correct Answer: C

,Rationale: The project manager's first responsibility is to address
conflict directly by facilitating communication between the parties.
Escalation (A) should be a last resort, reassignment (B) avoids the issue,
and ignoring it (D) allows the conflict to escalate. Facilitating dialogue
promotes team development and aligns with servant leadership
principles.



2. A project team is in the Storming stage of Tuckman's model. What
should the project manager do to help the team progress?



A) Provide clear direction and establish ground rules

B) Step back and let the team self-organize

C) Celebrate the team's high performance

D) Focus exclusively on technical deliverables



Correct Answer: A

Rationale: During Storming, team members may conflict over roles,
goals, and methods. The project manager should provide structure,
clarify expectations, and establish ground rules to help the team move
toward Norming. Stepping back (B) is appropriate during Performing,
and celebrating high performance (C) is premature.

,3. An Agile team's velocity has been declining for three consecutive
sprints. Team members seem disengaged during retrospectives. What
should the Scrum Master do?



A) Increase the number of daily stand-ups

B) Add more items to the sprint backlog to motivate the team

C) Use a retrospective activity that encourages open, blame-free
discussion

D) Report the declining velocity to senior management



Correct Answer: C

Rationale: Declining velocity and disengagement suggest the team may
feel unsafe or unheard. A blame-free retrospective using techniques
like "Start, Stop, Continue" can surface underlying issues. Increasing
stand-ups (A) adds pressure, adding work (B) worsens the problem, and
escalating (D) without understanding the root cause is premature.



4. A project manager is developing a responsibility assignment matrix
(RAM). The team uses the RACI format. What does the "C" represent?



A) The person who performs the work

B) The person who is ultimately accountable

, C) The person who must be consulted before a decision

D) The person who should be informed after a decision



Correct Answer: C

Rationale: In a RACI matrix, "C" stands for Consulted—those whose
input is sought before a decision or action. "R" is Responsible (does the
work), "A" is Accountable (ultimately answerable), and "I" is Informed
(notified after).



5. A project manager notices that a senior team member consistently
undermines decisions made during team meetings. Other team
members are becoming frustrated. What should the project manager
do FIRST?



A) Remove the team member from the project

B) Have a private conversation with the team member to understand
the behavior

C) Escalate the issue to the team member's functional manager

D) Ignore the behavior to avoid further conflict



Correct Answer: B

Document information

Uploaded on
September 26, 2026
Number of pages
133
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$29.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
supergrader
4.3
(3)
Sold
13
Followers
0
Items
3320
Last sold
1 week ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions