FDOT Final Estimates - Level 1
Save
Terms in this set (50)
What two types of Estimates are needed to pay for
Final & Progress Monthly
the work performed by contractors?
In case of discrepancies among the contract
Special Provisions documents, which document takes the highest
precedence?
Monthly Progress Contractors Recieve progress payments on the
Estimates basis of?
Preparation and Which of the following sets forth the Department's
Documentation Manual methods and procedures for preparing and
(PDM) checking final estimates?
Which Document contains a series of Specially
designed forms that show both original estimates of
Computation Books
quantities and the final quantities as measured ad
accepted?
Which Document contains alignment notes, cross-
Field Notebooks section notes, linear and area measurements and
dimension sketches?
Where are major changes during construction
Field Notebooks
documented and "as-built" conditions shown?
FEID, Contract number, What identification is needed to show on the front
General contents of the cover of a field book?
book
strike through, initial and When making corrections to a field book entry, you
enter correct data and should:
date
FDOT Final Estimates - Level 1https://online2pdf.com/remove-pdf-header-footer
1 of 5https://online2pdf.com/remove-pdf-header-footer
1https://online2pdf.com/remove-pdf-header-footer
, FDOT Final Estimates - Level 1.(exthttps://online2pdf.com/remove-pdf-header-footer)
Page 2 of 5https://online2pdf.com/remove-pdf-header-footer
FDOT Final Estimates - Level 1.pdfhttps://online2pdf.com/remove-pdf-header-footer
What should be started on the first lined page
INDEX
(page 1) of a field book?
Mark the page VOID and An entire page of a field notebook you are using is
reference it to a new incorrect, what do you do to correct the situation?
page showing the
correct information.
Construction will be "Check Levels" must be run at the start of a
done to design construction project to assure that:
elevations & final
measurements for
payment will be from the
same base elevations as
the original survey.
What should accompany final measurements so that
Sketches nonstandard measurements may be interpreted
accurately?
In the REMARKS column of most computation book
Source Documents
forms a reference should be made to the:
Never, gross tare must be When is it permissible to record only the net weight
included also on an asphaltic concrete tabulation form?
A limerock base course is constructed in two 13-foot
widths between station 19+40.20 and station
18,806 SY
84+50.00. What is the area of the base course to the
whole square yard?
4,840 How many square yards are in one acre?
Determine the area of the section (G) in the circle to
887.3 SF the tenth of a square foot. (NOTE: A= pi r(squared) x
(angle/360degrees)
If you have a benchmark at an elevation of 80.25'
85.70' and a back sight rob reading of 5.45', what is the
height of instrument (HI)?
If you have a pile cut off elevation of 50.00' and tip
40'
elevation of 10.00', what would your pile length be?