NERC Exam | Actual Questions and Answers Latest Updated
2026/2027 (Graded A+)
•
What is the calculation used for determining inadvertent interchange?
- ✔✔Net actual interchange minus net scheduled interchange
•
Which of the following would be a suitable use for a pseudo-tie?
- ✔✔Accounting for jointly owned generators
•
Which of the following entities may a Balancing Area provide interchange transaction information to?
- ✔✔PSEs involved in the transaction
•
Which of the following elements are NOT contained in the interchange transaction TAG?
- ✔✔Cost
•
A Balancing Authority can only implement interchange schedules with which one of the following?
- ✔✔Adjacent Balancing Authorities
•
Which of the following must be agreed on by the Sending and Receiving Balancing Authorities? 1.
Interchange Schedule start and end time 2. Energy profile 3. Ramp start time and duration 4.
Constraints
- ✔✔1, 2, & 3
•
Which of the following are responsible for confirming the ramp times and duration for interchange
transactions? 1. Sending Balancing Authority 2. Transmission Service Provider 3. Receiving Balancing
Authority 4. Scheduling Agent
- ✔✔1 & 3
•
Which of the following information is NOT necessary for a system operator to know in order to
implementan interchange schedule?
- ✔✔Source generator
•
If Balancing Area A has an interchange schedule export of 200 MW to Balancing Area B that started on
the hour, what would be the hourly integrated value for the transaction if the schedule were reduced to
100 MWon the half hour?
- ✔✔150
2026/2027 (Graded A+)
•
What is the calculation used for determining inadvertent interchange?
- ✔✔Net actual interchange minus net scheduled interchange
•
Which of the following would be a suitable use for a pseudo-tie?
- ✔✔Accounting for jointly owned generators
•
Which of the following entities may a Balancing Area provide interchange transaction information to?
- ✔✔PSEs involved in the transaction
•
Which of the following elements are NOT contained in the interchange transaction TAG?
- ✔✔Cost
•
A Balancing Authority can only implement interchange schedules with which one of the following?
- ✔✔Adjacent Balancing Authorities
•
Which of the following must be agreed on by the Sending and Receiving Balancing Authorities? 1.
Interchange Schedule start and end time 2. Energy profile 3. Ramp start time and duration 4.
Constraints
- ✔✔1, 2, & 3
•
Which of the following are responsible for confirming the ramp times and duration for interchange
transactions? 1. Sending Balancing Authority 2. Transmission Service Provider 3. Receiving Balancing
Authority 4. Scheduling Agent
- ✔✔1 & 3
•
Which of the following information is NOT necessary for a system operator to know in order to
implementan interchange schedule?
- ✔✔Source generator
•
If Balancing Area A has an interchange schedule export of 200 MW to Balancing Area B that started on
the hour, what would be the hourly integrated value for the transaction if the schedule were reduced to
100 MWon the half hour?
- ✔✔150