Construction quality management -
ANSWER
The performance of tasks, which ensure that construction is performed according to plans and
specifications, on time, within a defined budget, and a safe work environment.
Quality -
ANSWER
Conformance to properly developed requirements
Purpose of CQM -
ANSWER
The government's efforts, separate from, but in coordination and cooperation with the contractor,
assure that the quality set by the plans and specifications is achieved.
Contractor quality control function -
ANSWER
To assure that the completed project meets all quality requirements of the contract.
Contractor benefits of CQM -
ANSWER
Increased profit and production, better communications, planning, improved organizational skills,
and outstanding performance evaluations to obtain future contracts.
Two factors cause construction industry to become highly specialized -
ANSWER
Changing market and increased tech and regulations
Factors that will influence both the govt and construction industry in the future -
ANSWER
, New govt regulations, greater influence from customer, improvement of QC and QA requirements,
construction-oriented mgmt info systems, formal partnering involving stakeholders, more reliance on
design-build, more consideration for life cycle requirements, increased performance based incentives
Pre construction submittals -
ANSWER
Required prior to or at start of construction or the next major phase on a multi phase contract
Preconstruction submittals include: -
ANSWER
Scheduled and a tabular list of locations, features, and other pertinent information regarding
products, materials, equipment, or components to be used in work
Product data -
ANSWER
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions, systems and
equipment
Samples -
ANSWER
Fabricated or I fabricated physical examples of materials, equipment, or workmanship that illustrate
functional and aesthetic characteristics of material or product that establish standards
Design data -
ANSWER
Calculations, mix designs, analyses pertaining to a part of work
Test reports -
ANSWER
Signed by authorized official of laboratory that a material, product or system to be provided has
been tested in accord with specified requirements, unless otherwise specified, must have been done
within 3 years of date of contract award
Certificates -
GRADED A+| 100% CORRECT (VERIFIED SOLUTIONS)
Construction quality management -
ANSWER
The performance of tasks, which ensure that construction is performed according to plans and
specifications, on time, within a defined budget, and a safe work environment.
Quality -
ANSWER
Conformance to properly developed requirements
Purpose of CQM -
ANSWER
The government's efforts, separate from, but in coordination and cooperation with the contractor,
assure that the quality set by the plans and specifications is achieved.
Contractor quality control function -
ANSWER
To assure that the completed project meets all quality requirements of the contract.
Contractor benefits of CQM -
ANSWER
Increased profit and production, better communications, planning, improved organizational skills,
and outstanding performance evaluations to obtain future contracts.
Two factors cause construction industry to become highly specialized -
ANSWER
Changing market and increased tech and regulations
Factors that will influence both the govt and construction industry in the future -
ANSWER
, New govt regulations, greater influence from customer, improvement of QC and QA requirements,
construction-oriented mgmt info systems, formal partnering involving stakeholders, more reliance on
design-build, more consideration for life cycle requirements, increased performance based incentives
Pre construction submittals -
ANSWER
Required prior to or at start of construction or the next major phase on a multi phase contract
Preconstruction submittals include: -
ANSWER
Scheduled and a tabular list of locations, features, and other pertinent information regarding
products, materials, equipment, or components to be used in work
Product data -
ANSWER
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions, systems and
equipment
Samples -
ANSWER
Fabricated or I fabricated physical examples of materials, equipment, or workmanship that illustrate
functional and aesthetic characteristics of material or product that establish standards
Design data -
ANSWER
Calculations, mix designs, analyses pertaining to a part of work
Test reports -
ANSWER
Signed by authorized official of laboratory that a material, product or system to be provided has
been tested in accord with specified requirements, unless otherwise specified, must have been done
within 3 years of date of contract award
Certificates -