Pmt 3600V Exam 5: Advanced Program Management Concepts Questions And Answers With Verified Solutions 2026/2027 Update. Just Released

Document preview thumbnail
Preview 3 out of 24 pages

PMT 3600V EXAM 5: ADVANCED PROGRAM MANAGEMENT CONCEPTS QUESTIONS AND ANSWERS WITH VERIFIED SOLUTIONS 2026/2027 UPDATE. JUST RELEASED

Content preview

PMT 3600V EXAM 5: ADVANCED
PROGRAM MANAGEMENT CONCEPTS
QUESTIONS AND ANSWERS WITH
VERIFIED SOLUTIONS 2026/2027
UPDATE. JUST RELEASED


1. A project has a Budget at Completion (BAC) of $1,000,000. Currently, the BCWP is $400,000

and the ACWP is $450,000. If the remaining work is expected to be performed at the

budgeted rate, what is the Estimate at Completion (EAC)?

A. $950,000


B. $1,125,000


C. $1,000,000


D. $1,050,000


Answer: D


Conceptual Explanation: The formula for EAC when remaining work is performed at the

budgeted rate is EAC = ACWP + (BAC - BCWP). Here, EAC = 450,000 + (1,000,000 -

400,000) = 450,000 + 600,000 = $1,050,000.


2. Which of the following describes the ‘To-Complete Performance Index’ (TCPI) based on the

BAC?

A. (BAC - ACWP) / (BAC - BCWP)

,B. (BAC - BCWP) / (BAC - ACWP)


C. (BAC - BCWP) / (EAC - ACWP)


D. BCWP / ACWP


Answer: B


Conceptual Explanation: TCPI based on BAC is calculated as the work remaining (BAC -

BCWP) divided by the funds remaining (BAC - ACWP).


3. In the context of the EIA-748 Earned Value Management System (EVMS) guidelines,

Guideline 6 refers to:

A. Objectively measuring work progress


B. Defining the Work Breakdown Structure (WBS)


C. Establishing the Performance Measurement Baseline


D. Scheduling the work


Answer: D


Conceptual Explanation: Guideline 6 of the 32 EIA-748 guidelines focuses on scheduling

the work, ensuring a logical sequence of activities that support project milestones.


4. A Program Manager notices a Schedule Performance Index (SPI) of 0.85 and a Cost

Performance Index (CPI) of 1.15. Which statement best describes the project status?

A. Ahead of schedule and over budget


B. Ahead of schedule and under budget

, C. Behind schedule and under budget


D. Behind schedule and over budget


Answer: C


Conceptual Explanation: An SPI less than 1.0 indicates the project is behind schedule. A

CPI greater than 1.0 indicates the project is under budget.


5. What is the primary purpose of a Management Reserve (MR)?

A. To cover anticipated cost increases in work packages


B. To reward contractors for exceptional performance


C. To handle unknown unknowns and unforeseen project risks


D. To pay for scope changes requested by the customer


Answer: C


Conceptual Explanation: Management Reserve is an amount of the total budget withheld

for management control purposes to cover unforeseen risks or ‘unknown unknowns’

within the project scope.


6. Which contract type carries the highest risk for the contractor?

A. Cost Plus Fixed Fee (CPFF)


B. Fixed Price Incentive Firm (FPIF)


C. Cost Plus Incentive Fee (CPIF)

Document information

Uploaded on
September 23, 2026
Number of pages
24
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
$15.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TheStar
3.7
(140)
Sold
736
Followers
178
Items
28662
Last sold
1 day ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions