1. What is the primary purpose of erosion prevention and sediment
control (EPSC) measures on a construction site?
A. To increase the amount of disturbed soil
B. To prevent erosion and keep sediment from leaving the site
C. To eliminate the need for storm drains
D. To increase construction speed
Answer: B. To prevent erosion and keep sediment from leaving the site
,Rationale: EPSC measures are intended to control erosion at its source and
prevent sediment from being transported off the construction site into
drainage systems and receiving waters.
2. In Bowling Green, EPSC measures are required for land disturbance
exceeding what minimum area?
A. 250 square feet
B. 500 square feet
C. 750 square feet
D. 2,000 square feet
Answer: C. 750 square feet
Rationale: Bowling Green's construction-runoff requirements identify land
disturbances over 750 square feet as subject to EPSC measures.
3. What is the primary pollutant of concern commonly associated with
construction runoff?
A. Chlorine
B. Sediment
C. Oxygen
D. Salt
Answer: B. Sediment
,Rationale: Sediment is identified by Bowling Green as the principal
pollutant of concern from construction activity because disturbed soil can
be readily transported by stormwater.
4. What does BMP stand for?
A. Building Management Procedure
B. Best Management Practice
C. Basic Maintenance Program
D. Basin Monitoring Plan
Answer: B. Best Management Practice
Rationale: BMP means Best Management Practice and refers to measures
used to prevent or reduce stormwater pollution and associated impacts.
5. Which activity creates a particularly high potential for sediment runoff?
A. Maintaining established vegetation
B. Disturbing and grading exposed soil
C. Painting interior walls
D. Installing finished flooring
Answer: B. Disturbing and grading exposed soil
, Rationale: Clearing, excavation, grading, and other soil-disturbing activities
expose soil to rainfall and runoff, substantially increasing erosion
potential.
6. What should a contractor do before beginning regulated land-disturbing
construction?
A. Remove all existing vegetation
B. Obtain required approvals and have appropriate controls in place
C. Wait until the first rainfall
D. Discharge accumulated water into a storm drain
Answer: B. Obtain required approvals and have appropriate controls in
place
Rationale: Construction activities subject to stormwater requirements must
be properly permitted or approved before work begins, with required
BMPs implemented as applicable.
7. Who is ultimately responsible for implementation of an approved
stormwater plan under Bowling Green's construction-site stormwater
provisions?
A. The nearest property owner
B. The utility billing clerk
Stormwater Management for
Contractors Exam Practice Questions
And Correct Answers (Verified Answers)
Plus Rationales 2027 Q&A | Instant
Download Pdf
1. What is the primary purpose of erosion prevention and sediment
control (EPSC) measures on a construction site?
A. To increase the amount of disturbed soil
B. To prevent erosion and keep sediment from leaving the site
C. To eliminate the need for storm drains
D. To increase construction speed
Answer: B. To prevent erosion and keep sediment from leaving the site
,Rationale: EPSC measures are intended to control erosion at its source and
prevent sediment from being transported off the construction site into
drainage systems and receiving waters.
2. In Bowling Green, EPSC measures are required for land disturbance
exceeding what minimum area?
A. 250 square feet
B. 500 square feet
C. 750 square feet
D. 2,000 square feet
Answer: C. 750 square feet
Rationale: Bowling Green's construction-runoff requirements identify land
disturbances over 750 square feet as subject to EPSC measures.
3. What is the primary pollutant of concern commonly associated with
construction runoff?
A. Chlorine
B. Sediment
C. Oxygen
D. Salt
Answer: B. Sediment
,Rationale: Sediment is identified by Bowling Green as the principal
pollutant of concern from construction activity because disturbed soil can
be readily transported by stormwater.
4. What does BMP stand for?
A. Building Management Procedure
B. Best Management Practice
C. Basic Maintenance Program
D. Basin Monitoring Plan
Answer: B. Best Management Practice
Rationale: BMP means Best Management Practice and refers to measures
used to prevent or reduce stormwater pollution and associated impacts.
5. Which activity creates a particularly high potential for sediment runoff?
A. Maintaining established vegetation
B. Disturbing and grading exposed soil
C. Painting interior walls
D. Installing finished flooring
Answer: B. Disturbing and grading exposed soil
, Rationale: Clearing, excavation, grading, and other soil-disturbing activities
expose soil to rainfall and runoff, substantially increasing erosion
potential.
6. What should a contractor do before beginning regulated land-disturbing
construction?
A. Remove all existing vegetation
B. Obtain required approvals and have appropriate controls in place
C. Wait until the first rainfall
D. Discharge accumulated water into a storm drain
Answer: B. Obtain required approvals and have appropriate controls in
place
Rationale: Construction activities subject to stormwater requirements must
be properly permitted or approved before work begins, with required
BMPs implemented as applicable.
7. Who is ultimately responsible for implementation of an approved
stormwater plan under Bowling Green's construction-site stormwater
provisions?
A. The nearest property owner
B. The utility billing clerk