ADVANCED RIGGING COMPREHENSIVE
TEST PAPER WITH SOLVED QUESTIONS
◉ 2) What is the most important reason rigging hardware should
NOT be modified?
Answer: It could negatively affect its capacity
◉ 33) In the term (D/d ratio) the d is an abbreviation for:
Answer: Diameter
◉ 34) A document that outlines weights, crane configuration and
rigging requirements for a lift is called a:
Answer: Lift plan
◉ 35) A 1-inch wire rope sling in vertical basket hitch lifting a 24-
foot long, 36 inch diameter pipe,
Answer: 36 to 1
◉ 36) What is an LMI?
Answer: Load movement indicator
◉ 37) Location of electrical hazards on the job site should be
documented on a:
Answer: Lift plan
, ◉ 38) When forming a lift plan, a PRIMARY concern for the
person doing the rigging is:
Answer: Capacity of rigging
◉ 39) When using a wedge socket, the dead end of the rope is
secured in the socket by the:
Answer: Wedge
◉ 40) When erecting or stowing a swing-away lattice extension,
what should be used to control the movement of the extension?
Answer: Tag line
◉ 41) Planning for rigging is required:
Answer: Only when lifting any load
◉ 42) A lift plan MUST be completed by a:
Answer: Supervisor
◉ 43) Anchorage points for fall arrest harness for a single person
MUST be able to hold:
Answer: 5000 lbs.
◉ 44) Which of the following items are used for heavy rigging?
TEST PAPER WITH SOLVED QUESTIONS
◉ 2) What is the most important reason rigging hardware should
NOT be modified?
Answer: It could negatively affect its capacity
◉ 33) In the term (D/d ratio) the d is an abbreviation for:
Answer: Diameter
◉ 34) A document that outlines weights, crane configuration and
rigging requirements for a lift is called a:
Answer: Lift plan
◉ 35) A 1-inch wire rope sling in vertical basket hitch lifting a 24-
foot long, 36 inch diameter pipe,
Answer: 36 to 1
◉ 36) What is an LMI?
Answer: Load movement indicator
◉ 37) Location of electrical hazards on the job site should be
documented on a:
Answer: Lift plan
, ◉ 38) When forming a lift plan, a PRIMARY concern for the
person doing the rigging is:
Answer: Capacity of rigging
◉ 39) When using a wedge socket, the dead end of the rope is
secured in the socket by the:
Answer: Wedge
◉ 40) When erecting or stowing a swing-away lattice extension,
what should be used to control the movement of the extension?
Answer: Tag line
◉ 41) Planning for rigging is required:
Answer: Only when lifting any load
◉ 42) A lift plan MUST be completed by a:
Answer: Supervisor
◉ 43) Anchorage points for fall arrest harness for a single person
MUST be able to hold:
Answer: 5000 lbs.
◉ 44) Which of the following items are used for heavy rigging?