, During the contact administration phase, which functions Provide technical recommendations to support requests for subcontract consent
are the responsibility of facility engineers with reference to &
contract modifications? select two that apply. Participate in formal and informal design reviews and vendor conferences
The environmental Protection Agency uses the Hazard True
Ranking System to assess the relative threat associated
with actual or potential releases of hazardous substances
and is the primary screening tool for determining if a site is
included on the National Priorities List.
If you are planning an installation custodial contract, which Uniform Contract Format
contract format would you expect the contracting officer to
use for the solicitation and contract?
When responding to protests of the final award decision, Provide technical evaluation of protests to support government positions
which function is NOT normally performed by contracting
personnel?
Commitment accounting is required for Operations & False
Maintenance accounts.
If your installation's training ranges include habitat of True
endangered species, as part of Sustainable Range
Management you are required to minimize the effects of
operations on the habitat.
The Federal Facilities Compliance Act does not exempt False
agents, employees, and officers of the U.S. from personal
liability for any civil penalty arisign from acts or omissions
within the scope of their official duties.
Which decision making support system translates user Defense Acquisition System
needs into a weapons system or automated information
system.
When compiling the list of submittals to be requires in the -NOT- Review submittals to determine if the reports are necessary and if the
contract, which functions should be performed by the number of reports is appropriate
facility engineers? -NOT- Ensure approved submittals are referenced in the specifications
Which phase of the PPBE process has a primary purpose Programming Phase
to develop affordable Component resource packages
(programs) that cover 5 or 6 years and describe the levels
of forces, personnel, and money required to execute the
DoD strategy?
As the scope of waste management has come into focus, it True
has become clear that the preferred manner of managing
waste is to not generate it in the first place.
Which of the following appropriations is not associated with Military Construction
the Annual Funding Policy?
Which of the following is not one of the eight critical issues, Growth in size of military ranges
as defined by DoD, that present challenges to sustainable
range management?
You are working at a U.S. Army Corps of Engineers civil -NOT- Civil Works Appropriation
works facility that requires remediation. What funds would
you request to accomplish the remediation?