1. A process has a cycle time of 5 minutes per unit. What is the maximum
hourly production rate?
A. 5 units/hr
B. 12 units/hr
C. 15 units/hr
D. 20 units/hr
Answer: B
Rationale: Hourly production rate = 60 minutes ÷ 5 minutes per unit = 12
units per hour.
, 2. Which distribution is commonly used to model the time between
random independent events?
A. Normal
B. Uniform
C. Exponential
D. Binomial
Answer: C
Rationale: The exponential distribution models the time between events in
a Poisson process where events occur independently at a constant average
rate.
3. Which lean manufacturing tool is used to identify waste throughout a
production process?
A. Fishbone diagram
B. Pareto chart
C. Value stream mapping
D. Scatter plot
Answer: C
,Rationale: Value stream mapping documents material and information
flow, helping identify non-value-added activities and waste.
4. The purpose of a control chart is to:
A. Determine product cost
B. Forecast demand
C. Monitor process stability over time
D. Schedule employees
Answer: C
Rationale: Control charts distinguish common-cause variation from special-
cause variation to determine whether a process is statistically in control.
5. Which inventory model assumes constant demand and instantaneous
replenishment?
A. Newsvendor
B. MRP
C. Economic Order Quantity (EOQ)
D. ABC Analysis
Answer: C
, Rationale: The EOQ model assumes constant demand, fixed ordering costs,
and immediate replenishment to minimize total inventory cost.
6. The primary objective of ergonomics is to:
A. Increase machine speed
B. Reduce inventory
C. Fit the job to the worker
D. Increase advertising
Answer: C
Rationale: Ergonomics designs tasks, equipment, and environments to
match human capabilities and limitations.
7. In project management, the critical path consists of activities that:
A. Have the highest cost
B. Require the most labor
C. Have zero total float
D. Occur first
Answer: C
Practice Questions And Correct Answers
(Verified Answers) Plus Rationales 2026
Q&A | Instant Download Pdf
1. A process has a cycle time of 5 minutes per unit. What is the maximum
hourly production rate?
A. 5 units/hr
B. 12 units/hr
C. 15 units/hr
D. 20 units/hr
Answer: B
Rationale: Hourly production rate = 60 minutes ÷ 5 minutes per unit = 12
units per hour.
, 2. Which distribution is commonly used to model the time between
random independent events?
A. Normal
B. Uniform
C. Exponential
D. Binomial
Answer: C
Rationale: The exponential distribution models the time between events in
a Poisson process where events occur independently at a constant average
rate.
3. Which lean manufacturing tool is used to identify waste throughout a
production process?
A. Fishbone diagram
B. Pareto chart
C. Value stream mapping
D. Scatter plot
Answer: C
,Rationale: Value stream mapping documents material and information
flow, helping identify non-value-added activities and waste.
4. The purpose of a control chart is to:
A. Determine product cost
B. Forecast demand
C. Monitor process stability over time
D. Schedule employees
Answer: C
Rationale: Control charts distinguish common-cause variation from special-
cause variation to determine whether a process is statistically in control.
5. Which inventory model assumes constant demand and instantaneous
replenishment?
A. Newsvendor
B. MRP
C. Economic Order Quantity (EOQ)
D. ABC Analysis
Answer: C
, Rationale: The EOQ model assumes constant demand, fixed ordering costs,
and immediate replenishment to minimize total inventory cost.
6. The primary objective of ergonomics is to:
A. Increase machine speed
B. Reduce inventory
C. Fit the job to the worker
D. Increase advertising
Answer: C
Rationale: Ergonomics designs tasks, equipment, and environments to
match human capabilities and limitations.
7. In project management, the critical path consists of activities that:
A. Have the highest cost
B. Require the most labor
C. Have zero total float
D. Occur first
Answer: C