2026/2027 ACCURATE QUESTIONS
WITH CORRECT DETAILED
SOLUTIONS ||
100% GUARANTEED PASS
<NEWEST VERSION>
1. (From the Initial Stages of Project Development) Which of the following
could be considered stakeholders for a Civil Engineer project? Select ALL
that apply. - ANSWER ✔ Contracting Officer
Facility User
Communications Squadron Representative
Airfield Manager
2. (From the Initial Stages of Project Development) Which of the following
documents could be considered part of the project record? Select ALL that
apply. - ANSWER ✔ Independent Government Estimate
Quality Control Plan
Contractor Submittals
3. (From the Initial Stages of Project Development) A SABER contractor
submits a project invoice to the government that includes rental of a 25K
Forklift. The construction inspector for this project clearly recalls that the
only forklift used on the jobsite was a smaller 5K forklift, which costs
significantly less money to rent. Which document in the project record could
be used to dispute this claim? - ANSWER ✔ AF Form 1477 Daily
Construction Inspection Report
4. (From the Programming Fundamentals Lesson) You are working on a
project and determine a change order is needed because the beams were too
small to handle the roof load. However, this would exceed the approval
authority for this Construction project. What is a viable option for the project
, team? - ANSWER ✔ Resubmit the project to obtain appropriate approval
even if work must stop while the approval is obtained.
5. (From the Programming Fundamentals Lesson) If a project modifies an
existing facility to make it compliant with current codes and regulations, it is
likely a(n) _______ project. - ANSWER ✔ Repair
6. (From the Programming Fundamentals Lesson) Match the class of cost
estimate with its definition and use (not all options will have a match). -
ANSWER ✔ Class 1: Unit Price
Used to negotiate and compare bids with Contractors.
7. Class 3: Parametric Used for budgeting and making the official Programmed
Amount.
8. Class 5: Square Foot Used for long range planning when the scope is still
poorly defined.
9. (From the Project Management Plan Lesson) MSgt Jones is an extremely
competent SNCO that has years of experience working on high voltage
power projects. You have recently been appointed project manager for a new
power line installation on a remote part of your base. Gaining MSgt Jones
onto your project team would be an example of which type of risk? -
ANSWER ✔ Opportunity
10.75% rule - ANSWER ✔ A guideline used in project management to ensure
that 75% of a project's funding is secured before moving forward.
11.APF/NAF - ANSWER ✔ Appropriated Funds (APF) and Non-
Appropriated Funds (NAF) are types of funding sources for projects.
12.Basic programming thresholds - ANSWER ✔ The minimum requirements
or standards that must be met during the programming phase of a project.
13.Project Lifecycle - ANSWER ✔ The natural phases of any project,
including Planning & Programming, Design & Contracting, Construction,
and Closeout.