ExAC - Contracts and Divisions Exam
Questions & Answers (Grade A+)
What division would have general project requirements? -
correct answer ✅DIV 00
What division would contain info on software and document
managing be? -
correct answer ✅DIV 00
Which division is General Requirements -
correct answer ✅DIV 01
What is the general requirements section all about? -
correct answer ✅Summary of work, admin requirements, quality
requirements, temporary facilities, product requirements, closeout,
performance requirements,
Where would you find closeout requirements? -
correct answer ✅Div. 01 Gen reqs
Which division is Existing conditions -
correct answer ✅Div. 02
,ExAC - Contracts and Divisions Exam
Questions & Answers (Grade A+)
What's Div 03 -
correct answer ✅Concrete
Where would you find info about grouting? -
correct answer ✅Div 03 Concrete
What division is Masonry? -
correct answer ✅Div 04
What div is Concrete Masonry Units in? -
correct answer ✅Div 04 Masonry
What is in Div 05 -
correct answer ✅Metals
Would you include decorative metal in Div 05? -
correct answer ✅Yes
What division is Wood under? -
correct answer ✅Div 06
, ExAC - Contracts and Divisions Exam
Questions & Answers (Grade A+)
What division is plastics and composites under? -
correct answer ✅Div 06
What division would you put millwork info into? -
correct answer ✅Div 06 22 00
Where would you put structural plastics?? -
correct answer ✅Div 06 05 00
What div is insulation?? -
correct answer ✅Div 07
What is Div 07 called? -
correct answer ✅Thermal and Moisture protection
Where would you specify maintenance of fire and smoke
protection? -
correct answer ✅Div 07 Thermal and Moisture protection
Would you specify your air barrier in Div 08? -
correct answer ✅NO! Div 07 27 00 - thermal and moisture
protection, under air barriers
Questions & Answers (Grade A+)
What division would have general project requirements? -
correct answer ✅DIV 00
What division would contain info on software and document
managing be? -
correct answer ✅DIV 00
Which division is General Requirements -
correct answer ✅DIV 01
What is the general requirements section all about? -
correct answer ✅Summary of work, admin requirements, quality
requirements, temporary facilities, product requirements, closeout,
performance requirements,
Where would you find closeout requirements? -
correct answer ✅Div. 01 Gen reqs
Which division is Existing conditions -
correct answer ✅Div. 02
,ExAC - Contracts and Divisions Exam
Questions & Answers (Grade A+)
What's Div 03 -
correct answer ✅Concrete
Where would you find info about grouting? -
correct answer ✅Div 03 Concrete
What division is Masonry? -
correct answer ✅Div 04
What div is Concrete Masonry Units in? -
correct answer ✅Div 04 Masonry
What is in Div 05 -
correct answer ✅Metals
Would you include decorative metal in Div 05? -
correct answer ✅Yes
What division is Wood under? -
correct answer ✅Div 06
, ExAC - Contracts and Divisions Exam
Questions & Answers (Grade A+)
What division is plastics and composites under? -
correct answer ✅Div 06
What division would you put millwork info into? -
correct answer ✅Div 06 22 00
Where would you put structural plastics?? -
correct answer ✅Div 06 05 00
What div is insulation?? -
correct answer ✅Div 07
What is Div 07 called? -
correct answer ✅Thermal and Moisture protection
Where would you specify maintenance of fire and smoke
protection? -
correct answer ✅Div 07 Thermal and Moisture protection
Would you specify your air barrier in Div 08? -
correct answer ✅NO! Div 07 27 00 - thermal and moisture
protection, under air barriers