ExAc - Types of Construction Project
Delivery (CHOP 2.3.2 ) Exam Questions
& Answers (Grade A+)
Project delivery methods in the construction industry have evolved
in response to: -
correct answer ✅-increased owner requirements;
-more urgent time frames;
-increased demands for quality and safety;
-the need to reduce adversarial relationships in construction;
-economic pressures.
Project delivery -
correct answer ✅is a general term describing the comprehensive
process used to successfully complete the design and construction
of buildings and other facilities. The term is used to include all the
procedures, actions, sequences of events, obligations,
interrelations, contractual relations, and various forms of
agreement
Stipulated Price Contract (Design-Bid-Build) -
correct answer ✅the owner engages an architect to prepare the
design, drawings, and specifications;the owner hires a contractor by
competitive bidding to build the facility under a construction
contract (usually CCDC 2,
,ExAc - Types of Construction Project
Delivery (CHOP 2.3.2 ) Exam Questions
& Answers (Grade A+)
Stipulated Price Contract);the architect administers the contract,
and reviews and certifies the construction.
This design-bid-build form of project delivery is characterized by: -
correct answer ✅its three distinct phases;
-its two independent contracts between the architect and the
client/owner;
-the contractor and the client/owner,
-the linear sequencing of the process.
Advantages of design-bid-build -
correct answer ✅-widespread use and familiarity;
-clear roles assigned to each party;
-generally a transparent process
thorough resolution of the program requirements and design prior
to construction;
-Direct professional relationship between the client / building users
and the architect;
-has a known price before construction begins.
, ExAc - Types of Construction Project
Delivery (CHOP 2.3.2 ) Exam Questions
& Answers (Grade A+)
Disadvantages of design-bid-build -
correct answer ✅-Separation of design and construction restricts
useful communication;
-Clients sometimes perceive "extras" to be more prevalent and
costly in this form of project delivery than others
-The contractor is unknown when the construction documents are
prepared.
-Contracts, particularly for public sector projects, are awarded to
the low bidder who may not be well-qualified to do the work.
Prequalification of contractors on public sector bids is not common
Construction Management project delivery system -
correct answer ✅Construction management is a broad term
covering a variety of project delivery scenarios in which a
construction manager (CM) is added to the building team at an
early stage to oversee such elements as schedule, cost,
construction method, or building technology
A construction manager may be: -
correct answer ✅-an architect;
-a contractor;
Delivery (CHOP 2.3.2 ) Exam Questions
& Answers (Grade A+)
Project delivery methods in the construction industry have evolved
in response to: -
correct answer ✅-increased owner requirements;
-more urgent time frames;
-increased demands for quality and safety;
-the need to reduce adversarial relationships in construction;
-economic pressures.
Project delivery -
correct answer ✅is a general term describing the comprehensive
process used to successfully complete the design and construction
of buildings and other facilities. The term is used to include all the
procedures, actions, sequences of events, obligations,
interrelations, contractual relations, and various forms of
agreement
Stipulated Price Contract (Design-Bid-Build) -
correct answer ✅the owner engages an architect to prepare the
design, drawings, and specifications;the owner hires a contractor by
competitive bidding to build the facility under a construction
contract (usually CCDC 2,
,ExAc - Types of Construction Project
Delivery (CHOP 2.3.2 ) Exam Questions
& Answers (Grade A+)
Stipulated Price Contract);the architect administers the contract,
and reviews and certifies the construction.
This design-bid-build form of project delivery is characterized by: -
correct answer ✅its three distinct phases;
-its two independent contracts between the architect and the
client/owner;
-the contractor and the client/owner,
-the linear sequencing of the process.
Advantages of design-bid-build -
correct answer ✅-widespread use and familiarity;
-clear roles assigned to each party;
-generally a transparent process
thorough resolution of the program requirements and design prior
to construction;
-Direct professional relationship between the client / building users
and the architect;
-has a known price before construction begins.
, ExAc - Types of Construction Project
Delivery (CHOP 2.3.2 ) Exam Questions
& Answers (Grade A+)
Disadvantages of design-bid-build -
correct answer ✅-Separation of design and construction restricts
useful communication;
-Clients sometimes perceive "extras" to be more prevalent and
costly in this form of project delivery than others
-The contractor is unknown when the construction documents are
prepared.
-Contracts, particularly for public sector projects, are awarded to
the low bidder who may not be well-qualified to do the work.
Prequalification of contractors on public sector bids is not common
Construction Management project delivery system -
correct answer ✅Construction management is a broad term
covering a variety of project delivery scenarios in which a
construction manager (CM) is added to the building team at an
early stage to oversee such elements as schedule, cost,
construction method, or building technology
A construction manager may be: -
correct answer ✅-an architect;
-a contractor;